1300 Lakeshore Rd E has 28 municipal building permits on file in Ward 1. The latest recorded activity was a public permit dated Mar 9, 2026. Permits at this address represent $25MM+ in total declared construction value. PropertyLabs also identified 16 mapped permits within 2 km of this address.
ADDITION TO PLANT 1 BLOWER BLDG INCLUDING TANKS - G.E BOOTH WASTEWATER TREATMENT PLANT
INSTALL (2) NEW STANDPIPE SYSTEM FOR BLDG 150 AND 152
INSTALL (2) NEW STANDPIPE SYSTEM FOR BLDG 150 AND 152
INTERIOR DEMO W/ ALTERATIONS TO ACCOMODATE NEW EQUIPMENT IN PLANT 2 & PLANT 3 BLOWER BUILDINGS - G.E BOOTH WASTEWATER TREATMENT PLANT
INTERIOR DEMO W/ ALTERATIONS TO ACCOMODATE NEW EQUIPMENT IN PLANT 2 & PLANT 3 BLOWER BUILDINGS - G.E BOOTH WASTEWATER TREATMENT PLANT
16 mapped permits within 2 km, shown on the intelligence map above.
12 other addresses on Lakeshore Rd E with municipal permit records in Mississauga.
This address has 28 permit records in PropertyLabs' public history and is located in Ward 1. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Jul 31, 2026.
PropertyLabs compiled this permit history from municipal public records for Mississauga, ON. The latest recorded permit activity at 1300 Lakeshore Rd E is dated Mar 9, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 1300 Lakeshore Rd E in the PropertyLabs platform, along with alerts when new permits are filed at this address.
DEMOLITION OF MULTIPLE BUILDINGS (PLANT 1B) FOR FUTURE PLANNED INFRASTRUCTURE - G.E BOOTH WASTEWATER TREATMENT PLANT
DEMOLITION OF MULTIPLE BUILDINGS FOR FUTURE PLANNED INFRASTRUCTURE - G.E BOOTH WASTEWATER TREATMENT PLANT
DEMOLITION OF VARIOUS BUILDING TO MAKE SPACE FOR CONSTRUCTION OF FUTURE PLANNED INFRASTRUCTURE - G.E BOOTH WASTEWATER TREATMENT PLANT
STRUCTURAL & DUCTWORK ALTERATIONS DUE TO EQUIPMENT REPLACEMENT IN TOX3 BUILDING - G.E. BOOTH WASTEWATER TREATMENT PLANT
(1) NEW BUILDING & TANKS-G.E. BOOTH WWTP
NEW (1) STOREY PRE-FABRICATED MAINTENANCE BUILDING - G.E. BOOTH WASTEWATER TREATMENT PLANT
REVISION - INSTALLATION OF POTABLE WATER PIPING - G.E. BOOTH WASTEWATER TREATMENT PLANT
DEMOLITION OF EXISTING (2) STOREY MAINTENANCE BUILDING
EXTERIOR CLADDING & REPAIR - PARTIAL ROOF REPLACMENT - INTERIOR ALTERATIONS TO STAIR NO.1 & TRUCK LOADING BAY - MECHANICAL SYSTEM ALTERATIONS TO STAIR NO1 & 4TH FLOOR
RELOCATE DRAIN & (3) EXHAUST FANS ON ROOF NEW ROOF HATCH & ALTS TO SPRINKLER SYSTEM ON LEVEL 3 - G.E. BOOTH WASTE WATER TREATMENT PLANT
REVISION TO PERMIT # 19-5420 - INTERIOR ALTERATIONS TO SECOND FLOOR OF STORAGE COMPLEX - G.E BOOTH WASTEWATER TREATMENT PLANT
NEW CONCRETE WALL TO CLOSE THE OPENING TO THE THERMAL CONTROL FACILITY DEMO OF MIKE'S BLVD TUNNEL-CLOSE OPENING WITH CONCRETE WALL
CONNECT WATER & SANITARY FROM EXISTING BUILDING TO TEMPORARY FACILITIES
DEMOLITION OF (4) DECAN TANKS & THE TANK CONTROL BUILDING
INTERIOR ALTERATIONS- G.E. BOOTH WASTE WATER TREATMENT PLANT
REVISION TO PERMIT # 19-5420 - MODIFICATION TO THE ROOF OF THE RETURN SLUDGE PUMPING STATION - G.E BOOTH WASTEWATER TREATMENT PLANT
DEMOLITION OF VARIOUS BUILDINGS TO MAKE SPACE FOR CONSTRUCTION OF FUTURE PLANNED INFRASTRUCTURE - G.E BOOTH WASTEWATER TREATMENT PLANT
EXTERIOR ALTERATIONS - ALTERATIONS TO EXISTING ROOF - THERMAL OXIDATION BUILDING (TOX 1 AREA) - G.E. BOOTH LAKEVIEW WASTEWATER TREATMENT
NEW STORAGE BUILDING - G.E BOOTH WASTEWATER TREATMENT PLANT
DEMOLITION OF (2) CONTROL BUILDINGS (2) STORAGE SHELTERS UNDERGROUND TUNNEL & CONCRETE PADS
NEW PUMP STATION - G.E BOOTH WASTEWATER TREATMENT PLANT - COMPLETION
NEW PUMP STATION - G.E BOOTH WASTEWATER TREATMENT PLANT - FOUNDATION TO ROOF ONLY
ADDITION - G.E. BOOTH WASTEWATER TREATMENT PLANT