Building permit intelligence · Boston, MA
22 Concord Sq has 24 municipal building permits on file in Ward 4. The latest recorded activity was a gas permit dated Oct 29, 2024. Permits at this address represent $500K–$1MM in total declared construction value. PropertyLabs also identified 14 mapped permits within 500 m of this address.
Gas
Plumbing
Roofing
Replace electric water heater on 2nd floor.
install low voltage security system and low voltage fire alarm system
install low voltage security and fire alarm system
14 mapped permits within 500 m, shown on the intelligence map above.
12 other addresses on Concord Sq with municipal permit records in Boston.
This address has 24 permit records in PropertyLabs' public history and is located in Ward 4. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 3, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 22 Concord Sq is dated Oct 29, 2024. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 22 Concord Sq in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Remodle kitchen and replace water heater.
Rewire unit 3 lighting/outlets to code sub panel.
Frame new, non-loadbearing partition walls. Install new rough and finish plumbing in the bathroom and kitchen. Install new kitchen cabinetry, countertops and appliances. Install ne…
22 solar panel installation
Installing a 7.9 KW photovoltaic system.
Rewire first floor bathroom
In master bath remove and replace the existing vanity cabinet, sinks, faucets and countertop, remove all finishes and fixtures from the existing shower and install new plumbing fix…
Remove all interior finishes, plumbing and electrical fixtures, cabinetry and non load bearing partition walls. All work to be non-structural and interior.
Remodle 5th floor kitchen, laundry, bath and replace water heater. Remodle 2nd floor bath.
Install and wire recess lighting, cove lighting and switches.
Move exsting laundry sink.
Install Laundry on ground floor including cabinetry and sink.
Replace Hot water boiler.
Move esting hot water storage tank.
Install back flow for lawn sprinkler
Replace second and third floor decks within exisitng deck footprints and including new pier foundations. Install below grade drainage system per Civil Engineer's plan. Remove and r…
Erect wood fence on new concrete frost wall around perimeter of rear yard. Rear yard faces private way.
Second;and;third floor;deck replacement to match existing footprint per drawings and specifications by architect.; Not visable from a public way.
Electrical Fire Alarms · FA · Jul 29, 2026