Building permit intelligence · Boston, MA
248-270 Cambridge St has 79 municipal building permits on file in Ward 5. The latest recorded activity was a long form/alteration permit permit dated Jul 14, 2026. Permits at this address represent $5MM–$25MM in total declared construction value. PropertyLabs also identified 11 mapped permits within 500 m of this address.
Elec app. Per approval Historic Cert #26.0865 BH and engineer stamped drawings, install five awnings and reface an existing hanging sign. Work to be performed at 250 Cambridge St f…
Low-voltage cabling for access control card reader installation at retail bank branch.
Installation of Burglar Alarm security devices at Chase Bank 250 Cambridge St Boston MA 02114 (100861829-01)
JP Morgan Chase - Beacon Hill at 250 Cambridge Street Boston location. MISC Low Voltage HVAC Control Wiring SM 264065
Tenant fit out for a new bank
11 mapped permits within 500 m, shown on the intelligence map above.
6 other addresses on Cambridge St with municipal permit records in Boston.
This address has 79 permit records in PropertyLabs' public history and is located in Ward 5. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 248-270 Cambridge St is dated Jul 14, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 248-270 Cambridge St in the PropertyLabs platform, along with alerts when new permits are filed at this address.
56 telecom drops on the 1st floor of 248-270 Cambridge Street (250 Cambridge Street) for tenant JPMC Beacon Hill RS-267235
Tenant Fit-Out of former bank for new Chase Bank Branch.eplan
Fire alarm scope associated with a tenant renovation on the 1st floor, new devices and wiring to be installed and tied into an existing system.
Electrical scope associated with a tenant renovation on the 1st floor. New light fixtures, controls, receptacles, & panelboards to be installed throughout
24 Soil Borings
replace dry valve
add devices relocate existing devices and connect existing modules
Job Description: Column A-8 Temporary Shoring Purchase and installation of shoring posts and equipment as approved with the following included documents: - Simpson Gumpert & Heger…
add 1 speaker strobe to existing system , add 1 pull station and relocate 2 pull stations. add water flow module
Replace leaking valve on 1st floor
Replacing 10 corroded heads
Run overhead cables from existing 200 amp disconnect over to 480v step-down transformer for temporary power in the shed
Full bath renovation. Shower valve/drain, double vanity and toilet
Replacing some plumbing fixtures
Insurance claim work- Demo Drywall installation, prep work, paint Floor prep, replace damaged floor, damaged doors, cabinets and countertops including sink and disposal Electrical…
MASONRY RESTORATION & WATERPROOFING
INSTALL NEW PANEL AND BREAKERS DUE TO WATER LEAK. REWIRE THE KITCHEN AND REPLACE ALL THE RECEPTICLES AND SWITCHES WITH NEW ONES WITHIN UNIT #509
Replace panel and plugs and switches. In unit 203 due to a water leak.
AT7T proposes the following modification to the existing cell site: Swap existing antennas and remote radio units with new. The proposed modification does not increase the height o…
CHANGE DEVICES IN 2BEDROOM UNIT
replacing some plumbing fixtures
Insurance claim work: Multi-unit and hallway restoration, including: Drywall installation, prepping and painting, flooring prep and installation of damaged cabinets and countertops…
IN BUILDING #250 UNIT 101,202,302 I AM REPLACING THE ELECTRICAL PANELS AND BREAKER TO NEW ONES. IM ALSO REPLACING TWO BATHROOM EXAHUST FANS AND TWO IN WALL HEATERS WITHIN UNIT 101.…
Remove wire from breaker due to water damage. Install quad receptacles for restoration company. Replace device & breakers
rewire for lighting and power due to water leak unit #207, 309, 307, 607, one bedroom, living room, kitchen and bathroom. replace electrical panel with new one.
Complete repairs in units and community room. Burst pipe repair. Install ceramic tile to bathroom floor (multiple units). Removal of flooring.
Proposed Verizon Wireless antenna modification to existing rooftop installation. See submitted plans.
Masonry waterproofing, installing thur wall flashing & door pan
Walked through building to make safe for construction demo
Norel Service Co. Inc is contracted to replace the existing non-repairable/obsolete jockey and fire pump controllers.FIRE-Trol;See BFD permit SPRK1295613 and ISD electrical permit…
Disconnect existing wiring to obsolete jockey and fire pump controllers and replace as necessary to reconnect to replacement jockey and fire pump controllers.
Work being done in basement. Remove wire and boxed due to flood. Rewire walls for plugs. Install 60 LED 120v bypass 4ft bulbs. remove 2ft lights.
Replace public pacific panel and main breaker in unit
Renovation to an ATM vestibule
Relocate ATM vestibule.
Replacing existing Verizon Wireless antenna equipment.
Disconnect old water heater pipe up new one.
AT&T is proposing to install three (3) new panel antennas, nine (9) Remote Radio Units, (3) DC Surge Suppressors, (3) Fiber Trunk sand (6) DC Power Cables to their existing antenna…
Swap out three of four existing Verizon antennas on same mounts and swap out RRH in each of the three sectors, Certificate of Exemption filed herewith
Gas Water heater replacement , atmospheric same BTU rating
water piping for water heater replacement
64 Apartments, Retail, Parking, Grocery Store 36A, Hair Salon, Telecommunications &;;Bank COO for Offices (1st. Floor), Conference Room (2nd Floor);&; Residential Units 603, 604, 7…
64 Apartments, Retail, Parking, Grocery Store 36A, Hair Salon and Telecommunications and Bank Temporary Certificate for the;First Floor Office,;Second Floor Conference Room and Uni…
Building 66,550SF - Miscellaneous interior demolition (First floor office only) - Miscellaneous Masonry re-pointing - Interior metal hand rail refinishing and replacement - Roof re…
Retro fit of lighting for existing commercial office/apartment building
ELEV. BEING UP-GRADED BY OTHERS. ADDING TO EXISTING SYSTEM/CIRCUITS, (1) SMOKE DETECTOR WITH REMOTE LED, (2) RELAY MODULES (1 FOR FIRE HAT DISPLAY AND 1 FOR NEW HATCHWAY.) NO PRINT…
ADDING TO EXISTING FIRE ALARM CIRCUITS FOR ELEVATOR UP-GRADE UP OTHERS. BASEMENT: (1) SMOKE AND (1) RELAY FOR ELEV. HAT. 7TH FLOOR, (1) RELAY FOR NEW HATCHWAY. ALL DEVICES ARE NEW,…
Remove and replace 64 toilets, 5 lavatories, 5 kitchen sinks, 5 Dishwashers and Install 4 new ADA shower
Remove and replace 3 existing antennas with 6 new antennas. Replace 3 existing remote radio units with 6 new units. Install fiber/power connections as required. Work to be done wit…
Building 66,550SF • Miscellaneous interior demolition (first floor office only);• Miscellaneous Masonry Repointing • Interior metal handrails • Replace Roof • New exterior windows…
Extension to the base building fire alarm system to interface the new roof top AT&T satellite station. Adding (1) new speaker strobe and (2) addressable monitor modules to monitor…
64 Apartments, Retail, parking, grocery store. 36A, hair salon and telecommunications and Bank Alt165005 issued 9/21/2012 COO for Bank (First Floor)
Roof top Verizon Wireless antennas: Upgrade the existing antennas at same location and mounts and to add remote radio heads [RRH], surge arresters, junction boxes and cabling per p…
demolition of existing concrete floor
AT&;T received a Building Permit (ALT88367) in 2012 but is now adding additional steel to the shelter and placing the door on the west side of the shelter rather than the north. AT…
Installation of new;signs per BRA design approval 12-7-2011. To Read: TDBank;per plan
2ND FLOOR
A Geoprobe rig will drill borings and install monitoring wells at 7 locations within the vacant first-floor commercially zoned space at 250 Cambridge Street.
Fit-up of space for TD Bank Branch
Fit-up of space for TD Bank Branch
EXTENSION TO THE BASE BUILDING FIRE ALARM SYSTEM TO INTERFACE THE NEW ROOF A.T & T SATELITE STATION. ADDING TO THE EXISTING FIRE ALARM CIRCUIT ON THE TOP FLOOR TO INCORPORATE (1) N…
EXTENSION TO THE BASE BUILDING FIRE ALARM SYSTEM TO INTERFACE THE NEW ROOF A.T & T SATELITE STATION. ADDING TO THE EXISTING FIRE ALARM CIRCUIT ON THE TOP FLOOR TO INCORPORATE (1) N…
Replace boiler.
add service disconnects
Change Occupancy to include Bank.;;Interior demolition and fitout of a new space including finishes, plumbing, fire alarm, sprinklers, HVAC, Electrical &; Tel/Data.; ;A new aluminu…
Remove existing wood4' retaining wall and replace with 4' concrete and cement wall and replace existing set of stair to be same as existing. Work to be done in the court yard
Power outage emergency. Repair 5KV underground cable.
Scope of services to include drilling 2 test borings to a maximum depth of 20 feet inside the existing vacant retail space; coring the floor slab at up to 7 locations to evaluate t…
AT&;T is proposing to install (12) antennas and an 11.5' x 20' equipment shelter on the rooftop of 250 Cambridge Street (aka 8 Anderson Street). Verizon is currently installed on t…
(1) set of 16" channel letters and (1) 14" x 36" non-illuminated blade sign, double sided. Super Cuts - per BRA Design review
Legal Occupancy:; 64;apartments, Retail, Parking, Grocery Store w/#36A, Telecommunications, &; Hair Salon C/O For: Hair Salon Permit# Alt72488, Issued:; 5/24/11
Relocate one existing horn/strobe.
Demo of electrical systems add temp lighting
New storefront fitout
Short Form Bldg Permit · INTREN · Jul 24, 2026