100 Federal St has 220 municipal building permits on file in Ward 3. The latest recorded activity was a signes permit dated Jul 23, 2026. Permits at this address represent $25MM+ in total declared construction value. PropertyLabs also identified 3 mapped permits within 500 m of this address.
Signs
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
3 mapped permits within 500 m, shown on the intelligence map above.
4 other addresses on Federal St with municipal permit records in Boston.
This address has 220 permit records in PropertyLabs' public history and is located in Ward 3. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 100 Federal St is dated Jul 23, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 100 Federal St in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Fast Track Application
Fast Track Application
Fast Track Application
Fast Track Application
Fast Track Application
Fast Track Application
Fast Track Application
Electrical
Electrical
Electrical
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Plumbing
Plumbing
Fast Track Application
Fast Track Application
Electrical
Electrical
Fire Alarm
Fire Alarm
Fire Alarm
Renovations - Interior NSC
Renovations - Interior NSC
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Low Voltage
Fire Alarm
Fire Alarm
Low Voltage
Low Voltage
Fire Alarm
Low Voltage
Electrical
Electrical
Fire Alarm
Low Voltage
Reconfiguration of existing space on the 9th & 11th Floors. Includes minor demolition, upgrades to finishes, HVAC, Electrical, Fire Alarm and Sprinkler work.
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Common Area &; Restroom - 28th FloorALT1787368 Issued 10/21/2025
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Offices - 30 &; 31st FloorsALT1769286 Issued 9/15/2025
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate For Offices on the 28th floor;ALT-1784818 Issued 10/20/2025
Card Access, Video Surveillance and Alarm
Connecting 104 Furniture Feeds on the 30th Floor and 21 Furniture Feeds on the 31st floor for CIBC Private Wealth Management
Electrical Fire Alarm Work Associated with Tenant Fitout on the 10 Floor
Electrical Work Associated with Tenant fitout on the 10th Floor
25-099 OME has to run 24 new cat 6 to furniture area.
Install low voltage cable and system components associated with an AV system upgrade at 100 Federal Street for Stag Industrial
No work to be done - want to add use item "38" to allow live music on CO and follow up with licensing to amend / allow.Clarification: Adding live entertainment to existing restaura…
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and fitness Center;Certificate for Offices - 19th FloorALT1772313 Issued 10/10/25
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Offices - 20th floorALT1772321 Issued 10/10/25
5 security devices on the 29th floor of 100 Federal St for tenant STAG Industrial TK-256330
Renovations of existing space on the 10th Floor for new offices and common areas. Work includes removal of finishes, drywall, painting, flooring, ceilings, HVAC, Electrical, Fire A…
100 Fed 6th floor Cat6 migration. Install 2 new breakers into existing panel on 6th floor. MC S52752
Install control wiring for office fitout – (20) VAV’s, (26) PIU Valves with Tstats and (1) Electric Water heater @ 100 federal St – 29th Floor
100 Fed 6th floor Cat6 migration. Migrate Cat 6 LV cables to new IT room MC S52752
Connecting 21 furniture stations together at the TIAA CREFF office at 100 Federal St 19th floor.
Installing new fire alarm devices in the tenant space on floor 29. (STAG)
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Offices on 13th FloorALT1759700 Issued 8/12/2025
Installation of CCTV security devices at Bank of America 100 Federal St Boston MA 02110 (100861581-37)
Remodel of 29th floor tenant space. Space to be in white box condition.
Rough and Finish plumbing for office fit out include addition of new kitchen style sink with dishwasher, wellness room, 2 single use bathrooms, and two multiple use bathrooms. New…
Low Voltage Cabling 2 floors
Low Voltage Cabling for AV use. Low Voltage Cabling for Sound Masking. Floors 30-31
160 telecom drops on the 29th floor of 100 Federal Street for tenant Stag Industrial RS-257605
Job #20484 Brightcove 1st Floor Tel-data install
100 Federal St 28th floor Spec Suite Install control wiring (2) new VAVs, (1) Fan powered box and (2) PIU zones
Install control wiring for new HVAC equipment of an office fitout. Fan power boxes, exhaust fans and valves @ 100 Federal St. 30+31st floors
Job #20397 CIBC Floors 30 & 31 Tel-Data Install
Build out of 29th floor tenant space including new offices, conference rooms, open work areas, kitchen and restrooms, all new flooring, ceilings, lights & rework of existing sprink…
Replacement of fixtures in set of core restrooms. Rough and finish plumb new lavatories in core restrooms, new kitchen style sinks, and adding bottle fillers. Installation of new w…
Project 20213 - Tenant fit out of the 30th & 31st floor with new fire alarm to accommodate new architectural details
Project 20213 - Tenant fit out of the 30th & 31st floor with new lighting and power to accommodate new architectural details
The Renovation of a the 28th Floor Common Area of a multi-story Commercial Building.
The Renovation of the 28th Floor Spec Suite of a Multi Story Commercial Building.
Installation of video surveillance devices, intercom devices, access control devices, head end panels, and associated hardware. Terminate at the head end panel and test and program…
For sprinkler make safe on demo permit SF1786670. Permit costs covered on SF1786670.
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Lobby - 1st FloorALT1757152 Issued 8/15/2025;
Offices, 2 Banks, Restaurant 36A &; 37 And Parking and Fitness CenterCertificate For Offices;ALT-1747436 Issued 07/28/2025, SF-1747427 Issued 07/21/2025
Installing new fire alarm devices in tenant space on floor 28. (Spec Suite) Common Area.
Installing new fire alarm devices in tenant space on floor 28. (Spec Suite)
Project 31585 - Install 102 low voltage locations 19& 20th floors
25-100 O'Mahony & Sons will be renovating the common area & restroom on the 28th floor.
25-099 O'Mahony & Sons will be renovating the spec suite on the 28th floor.
The project consists of a renovation on the 28th Floor with selective removal of finishes and partitions, & new interior finishes and partitions with all necessary changes to MEP e…
19th FLOOR: Provide wiring, power, and lighting for interior renovation.
20th FLOOR:: Provide wiring, power, and lighting for interior renovation.
Make safe the 29th floor
Installation of 3 card reader access control system.
20th FLOOR: Install (2) Control Modules to the existing fire alarm system.
19th FLOOR: Install (1) Control Module to the existing fire alarm system.
Interior renovation on the 28th Floor with selective removal of finishes and partitions, & new interior finishes and partitions with all necessary changes to MEP equipment and fixt…
Installation of CCTV security device at Bank of America 100 Federal St Boston MA 02110 (100861581-35)
Interior alteration to existing tenant suite located on 20th floor of office building.
Interior alteration to existing tenant suite located on 19th floor of office building.
Cut & Cap Core Restrooms cut & cap 3 existing pantries on 29th Floor Cap Drain Lines & Venting & Water Lines to 2 pantries Cut & Cap cold water supply lines
Renovations to 29th floor suite. Removal of ceilings, walls, flooring. Sprinkler heads to be turned up per NFPA 241. Sprinkler work performed on separate ALT permit.
Installing fire alarm devices in tenant space. (Empower Lobby)
Installing new fire alarm devices in tenant space on floor 13. (Spec Suite D)
Demo existing boxes, install control wiring for (7) new VAV’s, (1) Fan power box + (1) Exhaust fan @ 100 Federal St 13th Floor Spec Suite
CIBC - 30 & 31st floors - New tenant buildout work includes: drywall, electrical /power/fire alarm/low voltage, sprinkler, plumbing , structural, HVAC and finishes.
Install new sink and hit water tank for spec suite project
28th Floor - Install control wiring for (2) Fan power boxes, (4) cooling only VAV’s and (1) Ex. Fan
Installation of low voltage telecommunications cable.
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;;Certificate for Fitness CenterALT1649659 Issue 4/1/2025 &; SF1694652 Issued 2/27/2025
renovation to 13th floor tenant space
Network wiring for Fitness center
Cut And cap two kitchen sinks one on 30th floor one on the 31st floor,
Installation of Access security devices at Coamerica Bank 100 Federal St Boston MA 02110 (100861388-02)
Empower Lobby renovation work to include demo of existing lobby, new walls, floors and finishes, sprinkler, electrical power/fire alarm/low voltage, HVAC
Relocate a total of (5) Walker Duct power outlets and (5) teledata outlets to accommodate new furniture configuration
Installation of Plumbing Fixtures and Plumbing Connections on the 28th floor of a Multi-Story private building.
The project consists of a fit out on the 13th Floor with selective removal of finishes and partitions, & new interior finishes and partitions with all necessary changes to MEP equi…
Project 19805 - Tenant fit out project with new fire alarm.
Project 19805 - Tenant fit out project with new lighting and power.
Moving modular furniture to support new layout on 15th floor.
Power, lighting scope associated with lobby upgrades
low voltage scope associated with lobby upgrades
Work is to be done on the 28th Floor of 100 Federal St. work is to include architectural upgrades and minor upgrades to MEP/FP. Interior office renovation including demise, ceiling…
Scope of work is for 100 Federal Street, 28th Floor. Work is to include minor architectural upgrades including flooring and ceiling work of an interior office space. renovation of…
Convert existing foam pre-action system to dry pipe sprinkler system on level 14M.
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Office - 13th FloorALT1699948 Issued 4/3/2025
Demolition to the 30th Floor and half of the 31st floor at 100 Federal St.
Sprinkler heads to be turned upright per NFPA 241 for demolition (demo to be associated with SF permit). Infill of stairs to include structural steel and concrete. Sprinkler heads…
Connect furniture feeds for 40 stations
Connected furniture feeds for 21 stationsOffice
Installation of CCTV security devices at Bank of America 100 Federal St Boston MA 02110 (100861581-33)
Removal and disposal of architectural finishes and MEP systems on floors 30 and 31
Empower - 18th floor remove wall and remove demountable partitions work not to effect Fire Alarm/ NO change to egress
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and fitness Center;;Certificate for Office space on the 3rd floor.ALT 1678194 Issued 1/27/25
Redgate 13th Floor Low Voltage Cabling 25-0093-10
Installation of card access devices for security purposes for the Redgate project.
Install control wiring for (11) VAV, (10) FCU and (10) valve controlled zones. Floor 13
;Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;;Certificate for Office Space on the 3rd Floor; ALT 1677061 Issued January 27, 2025
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;Certificate for Common Corridor and Common Areas on the 3rd floor.;ALT 1676912 Issued 1/27/25
expansion and renovation of the existing corridor on the 13th floor
Installing new fire alarm devices in tenant space on the 13th floor. (Common Corridor)
Install card access and cameras
100 Federal St Boston 3rd Fl – Veolia + Common Area Install control wiring for (14) VAV, (9) fan power boxes, (1) fan, (15) induction valves + (4) VAV cooling.
This project is located on the 13th floor of 100 Federal Street. It consists of Architectural upgrades to common areas including MEP/FP upgrades.
De-energized electrical testing and maintenance.
Install control wiring for (7) fan powered boxes, (4) VAV and (10) induction valves. @ 100 Federal St. 3rd Floor -First American Space
Installation of card access devices for security purposes for the Veolia project.
Audio Visual Conference Rooms
Veolia 3rd Floor
renovation to the 13th floor with new receptacles and Light fixtures
Rework of existing amenity space to include new shower valve trim and shower drains replacement, Rework of existing water closets from exposed flushometers to recessed in the wall,
Installing new and relocating existing fire alarm devices in tenant space on floor 13. (Redgate)
Fitness Center – Install control wiring for (1) VAV + (9) Fan power boxes
Steel and masonry repairs at the interior of the cooling tower area.
Installation of card access devices for security purposes for the 3rd floor Veolia project.
Addition of kitchen and wellness area to office space.
This project is on the 13th floor of 100 Federal Street. This project is an interior office fit out with changes made to architectural finishes. MEP FA/FP to be updated.
Power work for new turnstiles in elevator lobby
Low voltage work for new turnstiles in elevator lobby
Partial floor 1B interior renovation of an existing fitness center. Work includes non structural metal framing partitions, new finishes (Ceiling, flooring, paint, millwork) and new…
Electrical work associated with tenant fitout on Floor 1B.
Electrical Fire Alarm work associated with tenant fitout. Installation of 2 new strobes only and relocation of existing devices on the 1B Floor.
13th floor make safe demolition. Remove lighting, power, telecom
Interior renovations to 13th floor suite. Removal of interior flooring, walls, ceilings. Sprinkler heads to be turned up per NFPA 241.
Scope of work: (3) pantry sinks (1) hot water heater (2) water closets (2) urinals (1) floor drain
Partial floor 1B interior renovation of an existing fitness center. work includes non structural metal framing partitions, new finishes (Ceiling, flooring, Paint) and new and the r…
install low voltage communication cable.
Install kitchen sink, water heater expansion tank and water filter as part of 3rd floor fit out
Veolia Space -Install kitchen sink, two water heaters expansion tank and water filter as part of 3rd floor fit out
Install new toilets, water heater , urinals lavs and floor drains as part of bathroom upgrades
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;;Certificate for Corridor &; Restrooms on Floor 31ALT1655361 Issued 11/7/2024
Offices,; Banks, Restaurant 36A &; 37, Private Club ,Parking Garage, Fitness Center, Nail Salon, Auditorium, Café, Retails, ATM, Loading Dock and Mezzanine;Certificate for Offices…
Renovation to 3rd floor office space for Veolia. Work to include removal of existing architectural finishes and MEPs. Construction of new drywall partitions, carpet, paint, tile, g…
Renovation to 3rd Floor office space. Work to include removal of existing finishes & MEPs. Construction of new drywall partitions, glass, painting, carpet, tile, millwork, light fi…
Renovations to common corridor and core restrooms on 3rd floor. Work to include removal of existing architectural finishes and MEPs. Construction of new carpet, stone, tile millwor…
Job #18893 First American Tenant build out on the 3rd floor with new fire alarm.
Job #18893 First American Tenant build out on the 3rd floor with new lighting and general power receptacles.
Job #18892 Veolia Tenant build out on 3rd floor with new fire alarm.
Job #18892 Veolia Tenant build out on 3rd floor with new lighting and general power receptacles.
Job #18908 First American 3rd Floor Common corridor/restroom upgrades with new fire alarm.
Job #18908 First American 3rd Floor Common corridor/restroom upgrades with new lighting and general power receptacles.
Plumbing, HVAC and electrical makesafe on 3rd floor. Selective removal of architectural finishes, plumbing &; light fixtures throughout space. with alt1676912
Connect furniture feeds for 25 stations
Offices,; Banks, Restaurant 36A &; 37, Private Club ,Parking Garage, Fitness Center, Nail Salon, Auditorium, Cafe, Retails, ATM, Loading Dock and Mezzanine;Temporary Certificate fo…
Offices, 2 Banks, Restaurant 36A &; 37 and Parking and Fitness Center;;Certificate for Office Space - 23rd FloorALT1626288 Issued 8/12/2024
Install new floor drains, urinals, water closets, and lavs as part of bathroom upgrade
Interior renovation of corridor and restrooms on 31st floor. Scope to include framing on storage and wellness room and renovation of restrooms. Work to include new carpet, restroom…
Installing new fire alarm devices in tenant space on floor 31. (Common Areas)
1 Offices,; Banks, Restaurant 36A &; 37, Private Club, Parking Garage, Fitness Center, Nail Salon, Auditorium, Café, Retails, ATM, Loading Dock and Mezzanine;Certificate for Office…
Remodel of 32st floor common corridor and restrooms
Interior demolition and wall layout, on 31st floor, ahead of ALT1655361 being issued.
Relocating existing speaker/strobe on floor 23 and removing a speaker/strobe on floor 22. (Franklin Templeton)
Lighting, power modifications to portion of 22nd & 23rd floor @ 100 Federal Street 22nd Floor
low voltage modifications to portion of 22nd & 23rd floor @ 100 Federal Street 22nd Floor
Install wiring within office cubicles on 36th floor for Thomas Lee Partners
Installation of Burglar Alarm security device at Bank of America 100 Federal St Boston MA 02110 (100861581-29)
Installation of Access security devices at Bank of America 100 Federal St Boston MA 02110 (100861581-28)
low voltage modifications to portion of 22nd floor
Lighting, power, modifications to portion of 22nd floor
The Franklin Templeton Putnam modifications will include the transition of several workstation areas to offices/conference rooms and revise several existing workstations. Work incl…
Interior office renovation to include framing of non-structural walls, electrical, HVAC and fire alarm/ fire protection modifications. Work for Putnam Holdings on the 22nd floor.*A…
Elec app. Per BPDA approval 5-22-24 and stamped engineer drawings install Sign A: projecting sign over private property @ 48" x 38" @12.67 sf and 10' from grade to sign bottom. Sig…
Installing new fire alarm devices in tenant space on floor 22. (Franklin Templeton)
minor demo, add 6 pendant lights 3 exit signs
The project will include interior renovations of building a soffit and relocating lights. Demountable partitions will be installed. FP/FA not included.
Install low voltage cable and system components associated with an AV system upgrade at 100 Federal Street for THL
Offices,; Banks, Restaurant 36A &; 37, Private Club ,Parking Garage, Fitness Center, Nail Salon, Auditorium, Cafe, Retails, ATM, Loading Dock and Mezzanine, RestaurantCertificate f…
616 sound masking emitters devices on the 31st, 35th, & 36th floors of 100 Federal Street for tenant Thomas H Lee Sound Masking CZ-247050
Install Access Control and Surveillance Camera systems associated with the 35th & 36th floors tenant build-out and modifications on the 31st floor. The tenant occupying these floor…
100 Federal St. Boston. Floors 31, 35 + 36. Installation of control wiring for HVAC Equipment for floor fit-outs on floors 31, 35 + 36. The 31st floor is a partial floor.
Job #17761 Bank of America 10th Floor Install reused card reader and non-door hardware at new location.