Building permit intelligence · Boston, MA
308-316 Congress St has 165 municipal building permits on file in Ward 6. The latest recorded activity was a short form bldg permit permit dated Jun 4, 2026. Permits at this address represent $5MM–$25MM in total declared construction value. PropertyLabs also identified 13 mapped permits within 500 m of this address.
Erect 20x105 tent on 6/9/26, removal on 9/30/26.
Erect 20x90, 15x20 and 9x20 tents on 4/9/26, removal on 4/13/26.
Furnish & install 10 Sinks & 10 Faucet, Cut cap & remove wash bason 2nd floor,
Cosmetic upgrades to the 3rd floor gallery, bathrooms, and 2nd floor bathrooms, limited to tile, flooring, carpet, paint, lighting, ceilings, partitions and accessories. Cleaning a…
2nd and 3rd floor renovation at 308 Congress Street; Scope of work includes demolition and Make-safe, providing power for lighting, devices, and low-voltage conduits.
13 mapped permits within 500 m, shown on the intelligence map above.
12 other addresses on Congress St with municipal permit records in Boston.
This address has 165 permit records in PropertyLabs' public history and is located in Ward 6. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 2, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 308-316 Congress St is dated Jun 4, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 308-316 Congress St in the PropertyLabs platform, along with alerts when new permits are filed at this address.
3rd floor. Remove one piece shower unit. Repair wall and ceiling.
rough/ finish Kitchen sink on 5th floor
Low voltage alarm install for 308 Congress
Erect 20x105 tent on 6/8/25, removal on 10/1/25.
Erect 20x105 and 15x20 tents on 4/10/25, removal on 4/14/25.
Water piping for roof drain- Hood Bottle
Erect 20x105 tent on 5/31/24, removal on 10/02/24.
remove and replace with new fixtures in the bathrooms on the 6th floor
Erect 20x105 and 15x20 tents on 4/4/24, removal on 4/7/24.
Install wiring within office cubicles on 2nd floor for Cummings Construction Management at 330 Congress St
Erect 20x60 tent on 6/20/23, removal on 11/1/23.
Erect 20x105 and 15x20 tents on 3/27/23, removal on 10/27/23.
Re-locate 2 Horn Strobes, and 1 pull station following the office renovation permitted under ALT1289447
Museum, Offices, Store Exhibit Space and Retail / Café;Certificate For Exhibit SpaceALT1306165 Issued 5/13/2022
Museum, Offices, Store Exhibit Space and Retail/Cafe;;Certificate For Educational; Offices -6th Fl.-OnlyAlt 1300656 issued 3/18/22, SF 1300661 issued 3/3/22
Renovation of museum exhibit for the Boston children museum including demolition, New lighting and power in space.
Re-Locate existing notification devices in order to provide proper coverage for new setup of space.
Modify existing fire alarm layout to provide proper coverage for new museum display
Renovations; of Level 3-;;ceiling assemblies, insulation, all DFH trim, cabinetry, running trim, casework, wall coverings, all MEP items noted in drawings. Work in conjunction with…
Encore Fire Protection intends to relocate and reinstall existing fire alarm devices at the above referenced location per the Engineer’s proposed layout. All existing devices and w…
Tenant fitout. New lighting and modify power wiring.
Erect 20x110 tent on 5/1/22, removal on 11/3/22.
adding 6 cameras to the site
Small bathroom renovation, Replace 5 GFCI and 8-2x4 drop ins with LED.
Install toilets, lavs, and urinals on fifth and sixth floors.
replace (3) lights, 3 new switches, add 3 receptacles
BOSTON CHILDREN'S MUSEUM-CIEE MINOR TENANT FIT OUT OF SPACE FOR EDUCATIONAL OFFICES RELOCATE EXISTING SPRINKLER, FIRE ALARM, UPGRADE FINISHES, FF&E, NO CHANGES TO EGRESS.
BEGIN CONSTRUCTION UNDER ALT 1300656 MINOR RENOVATIONS TO EXISTING SPACE FOR CIEE EDUCATIONAL OFFICE THROUGH ROUGH INSPECTIONS PENDING ISSUANCE OF ALT. ALL FEE PAID UND ALT 3100656…
Interior renovations of 5th and 6th floor bathroom finish upgrade. This job will consist of updating existing finishes only.
Construct (3) 10x12 offices in existing open office space. Metal framing, drywall, wood doors in hollow metal frames, paint, resilient base, reposition light fixtures and devices.
Install 3 bay compartment sink
Furnish and install new 2 inch no hub cast iron waste from the hallway ceiling approx. 50 ft. Connect to the existing sanitary stack at the closest column. Run the new cast iron ab…
Replace existing green roof. Replace one existing exterior door. Replace guard rail.
Erect 20x60 tent on 5/31/21, removal on 11/30/21.
install cameras for Martin Richards Park
Install (1) 80" x 48" fabricated aluminum pan with applied dimensional letters, "Stonewall Kitchen, creators of specialty foods";;;;Per Fort Point Channel Landmark District approva…
Museum, Offices, Store Exhibit Space and Retail/Café Certificate for: Retail/Café Alt1078283 - 8/31/20
INSTALL ALARM SYSTEM
complete wiring of the Stonewall kitchen tenent fit up
Renovation of former MacDonald's space to a retail/café space for Stonewall Kitchen, approx 3000 sf. (signs are excluded from permit) eplan
Work to include: Demolition, rough carpentry to include siding, water proofing and insulation, window installation, new exterior door. No fire alarm and no sprinkler work- Milk Bot…
Renovation of existing Children's Museum Milk Bottle. Remove and replace light fixtures, receptacles and add new receptacles.
Install 1 dishwasher, 1 lavatory, 1 ice machine and 1 coffee
Select interior demolition of floors, walls, ceilings to prep for fitup of space for Stonewall kitchen in the former MacDonalds space next to the Boston Childrens Museum
Replace food serving area fixtures
Installing new fire alarm devices in space. (Stonewall Kitchen)
Erect 20x105 on 3/31/20. Removal on 10/01/20.
Museum, Restaurant. Offices, Store, Exhibit Space Certificate for:;Exhibit Space;on the;2nd floor -; Only ALT969849 - 7/9/19
Security System for 3078 Congress St 5th Floor. Card Access Reader, Door Controller
Erect 20x105 and (2) 6x20 tents on 11/12/19. Removal on 11/25/19.
Erect 15x20 and 20x20 tents on 10/24/19. Removal on 10/27/19.
Museum, Restaurant, Offices, Store, Exhibit Space Certificate for;the Offices on the;5th floor - Only ALT973673 issued 7/18/19;
Temp generator power for film production Set 10-2-19 Boston Children Museum
Installing new fire alarm devices in 2nd floor space. (BCM Playspace)
perform electrical modifications with new lighting on second floor of "children's play space exibit"
Category 6, data cablin only.
Erect (2) 20x100 tents on 8/13/19. Removal on 8/15/19.
plumbing renovation on the first floor in kitchen and bathroom
Renovations of space on the 5th Floor for EMPath. Work includes removal of finishes, patching, painting, flooring, HVAC, Electrical and Fire Protection work.
Plumbing renovation at 308 Congress St (EM Path)
Selective demolition of interior finishes and MEP's. New interior finishes and MEP's including fire alarm and fire sprinklers.
Upgrade FA system in office space to be renovated
Renovation of existing office space.
Erect 20x105 tent on 4/5/19. Removal on 10/4/19.
renovation to the 5th and 6th floor
Ovia -Interior renovations to finishes, remove and replace;carpet, paint on the sixth floor;work in conjunction with ALT909987
5th floor-Removal of interior finishes work in conjunction with ALT909987
Erect 20x115 tent on 10/6/18. Removal on 11/19/18.
Erect (2) 9x70, (4) 9x50, (3) 12x12 and 9x20 tents on 10/5/18. Removal on 10/8/18.
Erect 30x40, 9x30 and 6x10 tents on 7/25/18. Removal on 7/26/18.
Expand IP video
Installation of Kitchen sink in Studio B
There was a new wall built in the yellow room of the Boston childrens museum and we installed 3 tamper resistant duplex outlets to this new wall. 1 is old work and 2 are new work.
Erect 30x40 and 6x25 tents on 6/4/18. Removal on 6/5/18.
8'-0" partial height partition reconfiguration, remove door and infill opening. Add emergency exit sign.
Erect 20x115 and (2) 6x20 tents on 4/6/18. Removal on 10/5/18.
Security System card access 4 card readers cctv 4 out door cameras
Erect 20x1115 tent on 11/13/17. Removal on 11/19/17.
New finishes (carpet, ceiling, paint), some electrical work (new tel/data drops, new card access readers on doors. No fire alarm work.) No structural work, no life safety or fire p…
Erect (4) 9x70, (3) 9x50, 9x40, 9x30, 20x20 12x20 and (2) 9x10 tents on 9/16/17. Removal on 9/17/17.
Bathroom Renovations
Installing new fire alarm devices in new restroom on the 3rd floor. (BCM Restroom)
Renovation of existing 3rd floor toilet room
Third floor restroom renovation in Boston Children's Museum administration office space. New finishes in existing restroom: ceramic tile, acoustical ceiling, plumbing fixtures. Rel…
Erect 20x115 tent on 4/7/17. Removal on 10/7/17.
Placing a rolling stage/truck on the field of the Boston Children's Museum Park. No construction, only rental of stage. Going up 9/30/16 and taken down 10/1/16
Temporary generator power and electrical distribution for event outside the Boston Children's Museum on October 1st of 2016.
new fire alarm devices in tenant space
Renovation of Children's Museum Playlab
Erect 40x100 and 30x200 tents on 7/21/16. Removal on 7/24/16.
Erect 10x40 tent on 6/30/16. Removal on 7/24/16.
Boston Children's Museum, Playlab Interior Renovation. Reconfigure existing gallery space to create (2) new rooms. New MS/GWB partitions, new doors, new carpet and paint. Relocate…
Testing and maintenance of electrical distribution equipment
Erect 20x115 tent on 5/30/16. Removal on 9/29/16.
Erect 20x115 tent on 11/16/15. Removal on 11/18/15.
Restoration-Cutting & Pointing
S15-657, workstation wiring @ 303 Congress St.
Low voltage HVAC interlock wiring for 303 Congress Street, 4th floor, JME project # 15-2449.
Erect 10x20 tent on 7/2/15. Removal on 7/5/15
Erect (3) 20x100 tents on 6/25/15. Removal on 6/27/15.
Installation of plumbing for four lavs one kitchen sink two water heaters and one floor drain,
Erect 20x115 tent on 5/25/15. Removal on 9/25/15.
Erect 20x40 tent on 5/7/15. Removal on 5/11/15
Erect 20x40 tent on 10/24/14. Removal on 10/25/14.
Installation of My Sky Exhibit, July 2014.
Children's Museum signage at tower : Install 3 banners on 3 sides of exterior elevator structure per plans BRA and Historic Arch.Commission approved; works to be done by the respon…
; Construct a new 12' x 20' pile supported gangway pulpit. Install an owner supplied floating dock system and gangway. Supply and drive new mooring piles.
Erect (3) 20x100 tents on 6/25/14. Removal on 6/28/14.
Erect 20x115 tent on 6/10/14. Removal on 8/31/14.
Lunchroom Door hardware reconfiguration
Erect 20x115 and 25x25 tents on 11/17/13. Removal on 11/19/13.
Install new Cat 6 wiring
Portable theatrical lighting system for Boston Children’s Museum 100th birthday event. Lighting for various performance and event areas. Portable lighting system includes LED theat…
erect temporary performance truss structure 10/2-10/5 28 deep x 33 wide x 30 tall
Erect 25x55 tent and 16x16x24" high stage on 10/2/13. Removal on 10/7/13.
Furnish, deliver, rent, erect, dismantle and return 240 bleacher seats comprised of (2) sections, each 5 rows x 36' long.
1 st floor
Boston Children's Museum -; Installation of temporary projecting;banners, and one temporary sign on the north side of Building per BRA approved;plans.; All Banners / signage to be…
install 4 plugs
Demolition of Knee wall, electrical make safe, new carpet with vinyl base, Paint, and new outlets
To erect a 20x130 frame tent secured with water barrels. Install 8/8/13 and takedown 8/10/13.
Install Low Voltage Access Controll System at Boston Children's Museum.
Soil borings in public street.
Install Secrets of Circles Exhibit, May 2013.
Install seasonal outdoor seating for 92 persons;on private property, accessory to existing;Au Bon Pain cafe/restaurant. as per plans
Installing 30x60 frame tent and 12x12 frame tent beening set up april 5,2013 and date using 4,6/13 and take down 4/6/13
delivery 4/5/13 and date using 4/6/13 pick up date 4/6/13 for 100 anniversary children museum using 35,000 Generator Diesel
Install inflatable Arthur balloon on the roof of elevator shaft at Boston Children's Museum.
Temporary generator power and electrical distribution for event at the Children's Museum on February 8th of 2013.
Install new exhibit "BLUE MAN GROUP" on the 3rd floor of Boston Children's Museum.
1 st floor
Renovations to the existing Gift Shop in the Children's Museum lobby. Work to include construction of millwork display case, new track lighting, interior signage, install of rollin…
Install the exhibit "Framed: Step into Art."
Remove and reinstall floor.
Install Truck mounted generators for the support of a movie The Makeover. 9/14/2012 Generator to power Lights and Cameras. David Norcott is the electrician for the movie 508-631-06…
Erect 20x80 tent on 9/7/12. Removal on 9/8/12. Children's Musuem
We are doing some data drops in the new office space
Renovation of office space in the Children's Museum
minor non structural drywall partition demo, new drywall partitions, doors, painting, flooring, minor HVAC, electical
Installation of Inflatable Arthur on the exterior of Boston Children's Museum. Per engineers's affidavit from 4/1 thru 10/1
Installation of Native Voices Exhibit.-; new furniture.
Installation of Building Brainstorms exhibit 2011
Erecting 10x10 tents for Boston Food Fesival located on Boston Children's Museum Plaza, Children's Wharf, Laz Parking Lot (in front of Barking Crab) setup 9/30/2011 - takedown 10/2…
construct drywall metal stud wall, cut in door in drywall partition, new accoustical ceiling
Switchgear repairs
Installation of Inflatable Arthur on the exterior of Boston Children's Museum from april 1 thru october 1 per engineer's affidavit
Installation of "The Wizard of OZ" Exhibit on 3rd floor bay 7.
Telephone & computer wiring for three renovated locations
Making one office into 2 offices upstairs in the Children's Museum. We are moving some existing lights around and adding 2 switches and 2 outlets.
build 2 drywall partians, 2 doors and frames, rework HVAC, vinyl base, patch, paint and electrical.
Installation of temporary exhibit on the 3nd floor "Torn from Home" exhibit January 2010.
Installation of temporary exhibit on the 2nd floor "The Doll House" exhibit January 2010.
Erect 25x25 tent on 12/13/10. Removal on 12/15. No smoking under tent.
TEMP. GERERATOR AND DISTRO. FOR TENT EVENT. ONE DAY ONLY. AVAILABLE FOR INSPECTION AFTER 1PM 12-14-10 (TUESDAY). ELECT. JOHN 617-293-7387 GENI. OPERATOR JERRY 1 508 791 3366 (45KW)
Erect 20x30 tent on 12/14/10. Removal on 12/15/10. No smoking under tent.
Replace defective ground fault relay for the 2000A main disconnect and replace a defective panel meter in the switchboard at 300 Congress (the Childrens Museum)
2 temporary generators for street food festival. Power provided to two cooking tents and I stage for sound. Saturday morning inspection on 10/2 at 10am Adam Norcott 617-513-5969
Boston Local Food Festival October 2, 2010 from 11am - 5pm and the location of the stage is on Congress Street Bridge between Sleeper Street and Dorchester Avenue. The tent is 24 f…
Installation of temporary exhibit on the 2nd floor "Five Friends from Japan" Sept 2010.
Installation of temporary exhibit on the 2nd floor "Balancing Act".
Gas Permit · GAS · Jul 30, 2026