5 Channel Center St has 69 municipal building permits on file in Ward 6. The latest recorded activity was a other permit dated Jul 10, 2026. Permits at this address represent $25MM+ in total declared construction value. PropertyLabs also identified 4 mapped permits within 500 m of this address.
Other
replacement of gas water heater
removal and replacement of water heater
Installation of one deliveries sign plaque and window graphics and 23 3/4 wide x 96" high illuminated sign cabinet for "Genesis". Approved by landmarks and BPDA. Installed by the l…
Install wiring within office cubicles on 4th floor for Viralogic
4 mapped permits within 500 m, shown on the intelligence map above.
5 other addresses on Channel Center St with municipal permit records in Boston.
This address has 69 permit records in PropertyLabs' public history and is located in Ward 6. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 5 Channel Center St is dated Jul 10, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 5 Channel Center St in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Office &; Research FacilityCertificate for: Wet Labs - 3rd Fl.ALT1255413 issued 4/28/22
Office &; Research FacilityCertificate for: Wet Labs - 2nd Fl.ALT1255414 issued 1/2722
ACCESS SYSTEM WITH 6READERS AND 10 DOOR SWITCHES
22-0189-10 Viralogics Furnish and Install 43 cat 6 cables for office locations
Add EMT pipe and wire for future 120/208 circuits. Pull circuits from panels P24 & SB24. Add EMT pipe and wire for 4 furniture feeds.
Lab renovation
Office &; Research FacilityCertificate For Level 4 &; 5 Research Facility &; OfficesALT1255411 Issued 4/28/2022, SF1255418 Issued 10/12/2021
Office &; Research FacilityCertificate for Core/Shell for (Laboratory/Research) -Fls 1-6; -OnlyAlt 1204155 issued 9/21/21
Office &; Research FacilityCertificate For Research Facility &; Offices - Level 6ALT1255412 Issued 4/28/2022 , SF1255417 Issued 10/12/2021
We are adding a new 60amp feed, new 45 KVA transformer and 100a panel to existing space, we will then add 60 new receptacle circuits to existing space
Adding 80 receptacle devices to existing floor with light and power to existing panels
Basic wet lab fit out floor 3- new M/E/P's, HVAC, Flooring, Ceilings, fire alarm, fire protections as per plans.eplan
Basic wet lab fit out floor 6, new M/E/P's, HVAC, Flooring, Ceilings, fire alarm, fire protections as per plans.eplan
Basic wet lab fit out floors 4-5 , new M/E/P's, HVAC, Flooring, Ceilings, fire alarm, fire protections as per plans.eplan;
Job# 22-0055-10 -RING THERAPEUTICS 2 & 3 FL-Low Voltage Data only
Install wiring within offic ecubicles on 6th floor for Helix
Plumbing Scope associated with the 2nd and 3rd floor tenant fit out. Scope includes (3) added lab sinks, (3) added emergency safety stations, and (2) added floor drains.
Added tenant power to the 4th and 5th floor of the Virologic tenant space
Added power receptacles to 6th floor Helix tenant
Job# 22-0044-20 Helix Nanotechnologies, Inc 6th fl-Access Control
Job# 22-0045-10 Helix Nanotechnologies, Inc 6th fl-Tel-data
Job# 22-0055-10 Ring Therapeutics 2/3 floors-Low Voltage Data only
Install wiring within office cubicles on5th floor for Virallogic
Base Building data lines and security. 5th Floor tenant space data and security cabling only
Basic wet lab fit out floor 2- new M/E/P's, HVAC, Flooring, Ceilings, fire alarm, fire protections as per plans.eplan
Plumbing scope associate with 6th floor 6th floor tenant fitout. Scope includes (2) added laboratory sinks, (2) added emergency safety stations, and (1) floor drain for an ice mach…
Plumbing scope associated with 5th floor tenant fitout. Scope includes (3) added laboratory sinks, (3) added emergency stations, and (1) floor drain for an ice machine.
Begin demolition and construction pending issuance of ALT 1255412 Level 6 under review. All work will be in full compliance with 780 CMR, 521, CMR, 527 CMR. All fees have paid unde…
Begin demolition and construction pending issuance of ALT 1255411 Level 4 & 5 under review. All work will be in full compliance with 780 CMR, 521, CMR, 527 CMR. All fees have paid…
Begin demolition and construction pending issuance of ALT 1255413 Level 3 under review. All work will be in full compliance with 780 CMR, 521, CMR, 527 CMR. All fees have paid unde…
Begin demolition and construction pending issuance of ALT 1222414 Level 2 under review. All work will be in full compliance with 780 CMR, 521, CMR, 527 CMR. All fees have paid unde…
Modifications &; upgrades to existing Core/Shell for Laboratory/ Research /Development as approved by BPDA. M/E/P, FA, Sprinkler work as required to 6 story base building.eplan
5 Channel Center St, Boston, Fraunhofer. Misc. Low Voltage HVAC Control Wiring - PG - 219707
renovation to existing Fire Alarm system
Renovation work to existing branch wiring
Plumbing scope associated with the renovations at 5 Channel Center to provide new office and laboratory spaces.
Natural gas piping associated with the renovations at 5 Channel Center to provide new offices and laboratory spaces. Scope includes gas piping to a new boiler and standby generator…
INTERIOR NON-STRUCTURAL SELECTIVE DEMOLITION OF DRYWALL PARTITIONS,HVAC,DUST WORK, FF&E ON FLOOR B-6. FIRE ALARM & SPRINKLER TO REMAIN. DEMOLITION FOR FUTURE CORE/SHELL/TENANT FIT…
Mock of roof top units, to satisfy BPDA and Fort Point Chanel Landmarks. This will be a temporary mock and will only be there for 2 weeks. The structure will be built out of fire r…
pm of main gear at 1 CHANNEL CENTER Street
Interior renovations to existing tenant space. New Glass Entries adjustment of MEPs. No Structural, Life Safety or FA/FP.
Install 2 50 amp disconnects for test receptacle
Installation of a new 15-panel Solar Power Electrical Energy system
Installing a 4 KW photovoltaic system
supply and install numerous fixtures for Fraunhofer testing labs
offices and research facilities Alt136057 issued 7/10/2012, A125063 issued 3/18/2013, Alt62045 issued 12/30/2011 COO for Offices &; Research Facility (Basement and Floors 1, 2,3 &;…
Legal Occupancy:; Offices &; Research Facility Temporary Certificate of Occupancy for Base Bldg &; the basement thru the 6th Alt136057, issued: 7/10/12, Alt62045, issued: 12/30/11…
Removing partial scope of work from long form permit #ALT62045
Install wiring within cubicles on 2nd, 3rd and 6th floors.
Fraunhofer - Misc. Low Voltage Control Wiring AP 129889
Installation of an access control and video surveillance system cabling throughout (6) floors of 5 Channel Center.Card Readers (20), Cameras (6)
Install N-Star ductbank between 2 existing manholes
replace 100 exixsting light fixtures with new fixture
Install 200 new teldata outlets at 5 Channel Center in conjuncture with Gilbane Building permit on 1st,2nd, 3rd, 6th & basement
add new devices to existing system.
Tenant fitup of 5 floors
install 200amp 480volt temp service 75 k.v.a. transformer and 200amp 120/208volt service
Interior Construction of 6 floor office and lab space for Fraunhofer. Work to include concrete, misc metals, rough carpentry, millwork, thermal/moisture, roofing, sealants, DF&;H,…
INSTALL A NEW FIRE ALARM SYSTEM FOR THE BUILDING, MAIN PANEL, 22 SMOKE DETECTORS, 13 PULL STATIONS, 34 NOTIFICATION DEVICES, 1 DUCT SMOKE, CONNECTIONS TO TAMPERS AND FLOWS, GENERAT…
Low Voltage HVAC Control Wiring ~ Fraunhofer Institute Job #12-9483 (PAG)
NEW GAS SERVICE AND PIPING FOR 2 NEW BOILERS AND FUTURE PROVISIONS.
BUILDING RENOVATION- CORE PLUMBING SERVICES WITH FUTURE PROVISIONS.
Install new electric service, generator and fire alarm service, also furnish and install lights and receptacles for the building core on 6 floors plus the basemant
Change occupancy from Warehouse;to offices and research facilities. Base building work includes structural modifications, fire protection systems and some MEP systems.