Building permit intelligence · Boston, MA
669-675 Albany St has 20 municipal building permits on file in Ward 8. The latest recorded activity was a electrical permit permit dated Jun 5, 2026. Permits at this address represent $1MM–$5MM in total declared construction value. PropertyLabs also identified 1 mapped permit within 2 km of this address.
Solomon Carter Fuller Mental Health Center - (85 E Newton St.) Install new DGP, (3) CTs, install CAT6 from gas meter to DGP, install 18/4 to water meter. SOUR141X
Install a new 200A 480V branch circuit from the MDP to feed a new 150KVA step down XFMR which will feed a new 400A 120/208V three phase panelboard that will power (2) new dual port…
Install (6) duplex receptacles and (2) GFI receptacles.
Solomon Carter AHU Upgrades. 85 E. Newton Street. Misc. Low Voltage HVAC Control Wiring . AG-232106
Rework existing bathrooms for ADA compliancy.
1 mapped permit within 2 km, shown on the intelligence map above.
9 other addresses on Albany St with municipal permit records in Boston.
This address has 20 permit records in PropertyLabs' public history and is located in Ward 8. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 669-675 Albany St is dated Jun 5, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 669-675 Albany St in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Remove 4 fixtures from existing bathrooms and replace 4 existing
Solomon Carter Fuller - Cooling Towers 85 E. Newton Street. Misc. Low Voltage HVAC Control Wiring - PG-220731
Installation of card access devices for security purposes on the 4th Floor SCF.
provide new electrical distribution for elevators 1,2,3,4,5 and 6 and replace 500KW generators with (2) 250KW type.add area of rescue on all floors
Add Fire Alarm devices in generator and elevator machine rooms
provide temporary SER cable to tenth floor generator room from temp generator at ground floor dock
Wiring of 30 voice/ data locations
Provide new electrical distribution for elevators 1,2,3,4,5,and 6.Provide and replace existing 500KW generator and controls with (2) 250KW generators on the 10th floor.Also provide…
Provide install fire alarm monitor and control modules in machine and generator rooms
Provide SER cable from ground floor to the 10th floor generator room.Cables will be installed on the exterior of the building to Re feed the transfer switch of the recently downed…
provide temporary power to construction trailers
HAM101X - Power Demo (make safe only - removal from building by others) for (2) Cooling Towers and the Power Wiring for (1) New Cooling Tower which will take the place of the (2) t…
Install fixtures, switches, and receptacles.
BUMC E Bldg Basement Auditorium, Misc. Low Voltage HVAC Control Wiring AP-163208
install sink and EEmax hot water heater E6