Building permit intelligence · Boston, MA
1006-1022 Massachusetts Av has 122 municipal building permits on file in Ward 8. The latest recorded activity was a electrical permit permit dated Jul 1, 2026. Permits at this address represent $5MM–$25MM in total declared construction value. PropertyLabs also identified 2 mapped permits within 500 m of this address.
Provide power to one (1) new replacement condenser and one (1) new replacement AHU.
Install of (3) Level 2 EV Chargers
test
Job location is 1010 Mass Av. Activity is on Floor 2, for the Boston Public Health Commission (BPHC). Scope - placing outlets and light switches for new office buildout.
Existing floor plan in office to be re-done.2 office space build out w metal studs go all the wat to ceiling and anchored, pressure treated wood underneath with water proof padding…
2 mapped permits within 500 m, shown on the intelligence map above.
12 other addresses on Massachusetts Av with municipal permit records in Boston.
This address has 122 permit records in PropertyLabs' public history and is located in Ward 8. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 1006-1022 Massachusetts Av is dated Jul 1, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 1006-1022 Massachusetts Av in the PropertyLabs platform, along with alerts when new permits are filed at this address.
test
test
TEST app
TEST APP - raze
1010 MASS AVE ISD- install 1 power pole for 2 desks, 20 amp circuit breaker, 2 data lines, relocate outlet for copy machine in area across from electrical inspector station.Remove…
TEST app
TEST app
test
TEST APP - more info provided
New gas connections for 10 replacement RTUs serving 1010 Mass Ave Annex wing.
Install 200A sub panel Install (3) terra wall box EV stations on exterior
Replacing 4 banners, recovering existing awnings, replacing box sign on existing pole,and remove replace cut letters on Annex for City of Boston
Add one smoke detector and remote alarm indicator in electric closet 409 of 1010 Mass Ave. Note: Permit Fee is waived
Install low voltage communications cabling on the 4th floor of 1010 Mass Ave Permit fee Waiver is attached
Add smoke detector to electrical closet and RAI on to existing fire-alarm system
Provide power to furniture feeds, receptacles and DATA wiring, add 1 light fixture and switch.
Interior renovation of office space. Work includes electrical, flooring, acoustical ceiling, wall &; door carpentry and painting on 4th floor. only. No sprinkler,; fire alarm, or s…
Furnish and install (1) 6 strand SM fiber from 1st floor animal control cabinet to 1st floor MDF in Division of Transitional Assistance. Furnish and install (1) 6 strand SM fiber f…
Remove and replace 3-heating rooftop Energy recovery units
Disconnection of old (3) MAU's & Reconnection of (3) New ERV's. Disconnection of (31) Heat Pumps & Reconnection of (31) New Heat Pumps. Power to (31) 120v Fire Smoke Dampers
Installation of new (6) duct smokes serving rooftop (3) ERV's. Installation of (31) new Fire Smoke Dampers with Smoke Detectors.
It is for installing 11-dual data locations on 1st. floor for Police accountability and transparency. I have included the permit waiver fee letter from Laurie at City Hall @ 1010 M…
Replace 3 ERV's, 31 Heat pumps and associated ductwork and power.
Water heater replacement at 1010 Massachusetts Avenue.
Remove and replace 3-heating boilers
Disconnect/ Demo 2 boilers, pumps in Penthouse- Wire 3 boilers, pumps in Penthouse; Disconnect/Reconnect 3-MAU's (1-3) located on roof.
Demo - two boilers, pumps ductwork and 3 rooftop units in preparation for ALT permit to be filed once drawings are complete
TEST
test
test
test
TEST APP
install 2-data locations from animal control data cabinet to 1st floor security desk to support new security equipment @ 1010 Mass Ave 1st fl
Remove and replace 3 antennas and 3 radios. Replace cabinet wit equipment rack.
Remove and replace 3 cell antennas.
One for one retrofit of existing lighting fixtures to LED fixtures.
1010 Massachusetts Avenue - low voltage controls wiring on HVAC Units.
Disconnect 63 heat pumps and reconnect new pumpsColing tower replacement. Disconnect old tower equipment and pumps. Reconnect new tower equipment and pumps.
T-Mobile to replace three (3) antennas, replace three (3) RRU’s, replace one (1) equipment cabinet with one (1) equipment rack and add three diplexers to the existing telecommunica…
Work for 1010 Mass Ave 5th fl - Single mode 6 strand armored fiber from 5th fl. data cabinet down to 1st. fl. Animal control space.
T-Mobile proposes to replace three (3) antennas on an existing wireless communications facility. eplan
Replacement Meter Socket with New.
testing the system
Remove and replace number displays. Work to be done at 1010 Mass. Ave., fifth floor.
Upgrade T-Mobile's service from the basement switch gear to roof top pent house. Provide 125A 480V power feed to proposed disconnect and 50KVA transformer in basement. Feed from th…
Remove and add 3 antennas and hybrid coax lines.
T-Mobile proposes to replace six (6) antennas, three (3) RRU's and add three (3) 1-1/4” (6x12) Hybrid cables to an existing telecommunications facility. [ePlan]
4th floor property management add power @ 1010 Mass Ave ISD
4th floor renovation add data in half wall @ 1010 Mass Ave ISD
4-emergency wall phones on the 4th floor and 1-dual data location for Parks Commissioner on the 3rd floor @ 1010 massachusetts avenue
build a non load bearing;wall on fourth floor to accommodate storage for adjoining offices
Install &; furnish emergency phones on the 5th fl @ 1010 Mass ave work for City of Boston
5th fl Housing division at 1010 Mass Ave work for City of Boston. Install (5) power poles for furniture feeds . Wall feeds for furniture.
Furnish & install (28) TD locations @1010 Mass Ave
Renovations to fifth floor. Project number 7143
Interior renovations and updating of finishes at 5th floor office space area.
Install (4) 12 Strand Fiber Cables for Data Network Boston Health Commission 1rst, 2nd and 5th floors No Permit Fee--See City of Boston Letter
Remove door and window, reframe and replace in new location 4th floor BFD/ISD shared space. ;
General electrical maintenance to change ballasts and lamps throughout all floors in building.
1st Floor relocate and add power for new furniture.
Wire 2 ductless split air conditioning units in server room ( Boston health services 6th floor
electrical make safe to 5th floor demo of office
Renovate existing 5th floor offices in the Planning Division. Minor Electrical Work.
Installation of three antennas at existing arrays with associated remote radio units. All new equipment to be painted to match existing antennas located on the roof penthouse. Exis…
Replace 40 Gal. Electric HWH
T-Mobile proposes to remove three (3) antennas and add three (3) similar size antennas to a communications facility on the rooftop of 1010 Massachusetts Avenue.
Installation of low voltage cabling with video conferencing screen and speakers for the Executive conference room
New 30A/1P Receptacles &; Wiring For new data Racks On Floors 3, 4 &; 5 of 1010 Mass ave Bldg.
Low Voltage Re-Wiring for floors 3,4 &; 5
Low Voltage - Card Reader Add
Adding 2nd means of egress to the 3rd floor Parks Department.
Adding;petition walls in the planning and zoning division, electrical and LV permits obtained as well.
5th floor work in the Planning, BOA and Call Center area.; Adding outlets and a Furniture (Whip).
adding location for data lines
adding location for data lines
5th floor bathroom renovation. Wire electric water heater
Removed 4 power poles and relocated 2 switches
New shower 5th floor
Projectdox test
Excavate partial driveway to expose foundation to waterproof.
new circuits and outlets for the 5th floor ISD,planning and examiners areas
Installation of disconnect switches, receptacles,and pit lights for main and north elevators
Installation of smoke detectors and modules for recall at north and main elevators
1010 Mass. Ave. Boston Public Health security card reader
test
test
replace all the exterior light fixtures around the entire building, add 2 new fixtures
install outlet
install outlet, 30 amp breaker
Installing 6 TV
Modernization of three existing elevators and electrical upgrades
run new feeders for outlets for new TV installations, also for desk top outlets. install sub panel in electric rooms if needed
test
1010 Mass Ave. 2nd floor South upgrade removal existing carpet and install new VCT. Repainting all walls. Adding partitions to make two new rooms from open space. Extending one roo…
upgrade 50 amp to 100 amp feed for Telco equipment
rework the wiring for new offices and cubicles, 2nd Fl of 1010 Mass Ave.
low voltage data wiring
remove existing cabinets in breakroom .install new cabinets and granite
Modification of an existing wireless communications facility, all as shown on the plans.
Counter Top Replacement at the Boston Fire Prevention Division of the Boston Fire Department
test
Rough and finish plumbing for one new kitchen sink on the second floor
Install new 2-pole 60 Amp circuit for Cellular battery cabinet.
test
test
test
Interior repairs dry wall
replace one existing BTS Cabinet with one of equal size, shape and weight.
test
test
test
test
ADDING AN AVAILABLE TEMP SERVICE FOR SWING LIFTS FOR MASSONARY WORK WHILE PIONTING THE BUILDING
Masonry restoration
Remove water damaged sheetrock and ceiling tiles from building AND DRY WALLS
diconect gas pipe for the new roof to be installed and reinstall the same gas pipe after the new roof is in place.paint the pipe if it is rusted.
remove and replace 12 roof drains.remove and reinstall gas pipe as needed for the roof too be installed.