Building permit intelligence · Boston, MA
1165 Massachusetts Av has 142 municipal building permits on file in Ward 7. The latest recorded activity was a signes permit dated Jul 15, 2026. Permits at this address represent $25MM+ in total declared construction value. PropertyLabs also identified 3 mapped permits within 500 m of this address.
Signs
Signs
Other
Other
Other
Turning up sprinkler heads and returning them to proper use after installation of support steel for roof top units. Full cost of permit paid under ALT1686195.
3 mapped permits within 500 m, shown on the intelligence map above.
12 other addresses on Massachusetts Av with municipal permit records in Boston.
This address has 142 permit records in PropertyLabs' public history and is located in Ward 7. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 1165 Massachusetts Av is dated Jul 15, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 1165 Massachusetts Av in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Replacement of roof top units including the installation of supplemental steel to hold the new units.
Low Voltage
Gas
Electrical
Electrical
Plumbing
Fire Alarm
Fire Alarm
Fire Protection/Sprinkler
Fire Protection/Sprinkler
Low Voltage
Electrical
Renovations - Interior NSC
Excavation Borings Test Pits
Change Occupancy
Plumbing
Renovations - Interior NSC
Fire Alarm
Low Voltage
Electrical
Electrical
Electrical
Fire Alarm
Low Voltage
Plumbing
Other
Other
Low Voltage
Low Voltage
Minor renovation to existing EVERSOURCE Community Affairs Office. New drywall finishes and FF&E. All work in full compliance with 780 CMR, 521 CMR, 527 CMR.
Small remodel of existing 3 offices with 2 x 2 lighting, monitors & poke thrus
Interior renovations
Eversource Operations Facility- Installation of site Security Fencing as required by AHJ. Fence installed on Massachusetts Ave, East Cottage, Norfolk and MASSDOT Commuter Rail abut…
upgrade power and lighting new area
low volt
1st floor low voitage
upgrade for powerand lighting in new arer
Installation of Federal Utility Regulatory Commission Policies Act - Critical Infrastructure Protection (CIP) - Physical Security Directives; CIP-014-1, CIP-014-2 "Asset Physical H…
1 floor office
upgrape of vp arca lighting cores rec
Remove six existing cubicles and creating two office spaces.
Electrical assembly of office furniture partitions in A Building, ground floor supervisor's office.
Install low voltage control wiring on new HVAC equipment in Building A Boston service center SIEM431X
Install breakroom sink with ejector pump
Furnish and install low voltage electrical work for Supervisor's Office renovation in "A" Building, Ground floor.
Electrical work for renovation of supervisor's office in "A" Building on ground floor. Work includes installation of (1) 150a 120/208v 3p 4w panelboard.
Office re-model. Installing 4 smoke detectors, 4 horn/strobes, 2 strobes, and 1 pull station.
Eversource -; Interior renovations to approximately 2,900 Sq Ft of existing Office space. Including relocating interior non-load bearing masonry and drywall partitions. Remove and…
Locker room/ Bathroom renovation
Interior remodel. Installing 5 new strobes in remodeled locker rooms and 2 smoke detectors in new offices.
Interior renovations to existing Locker Rooms, Break Room and Office in Building B. Including masonry partitions, drywall partitions, acoustical ceilings. Modifications to existing…
Electrical low voltage work for renovation of Locker Room and Office in B Building Warehouse.
Electrical work for renovation of Locker Room and Office in B Building Warehouse. Includes installation of (1) new panelboard 100 amp 120/208 volt 3p 4w. Also includes installation…
2nd floor
2nd floor
Office renovation on 2nd floor (Two Fire Alarm devices to be relocated)
exterior slab repairs/replacement of existing dock.
exterior slab repairs and replacement to existing dock. Major cost is placed on alt883581 pending.
Sixteen borings advanced in the exterior of existing site buildings. 12 borings will be advanced to 15 feet below grade. 4 borings will be advanced to 50 feet below grade or to bed…
Added Network drops for Computers, phones, TV's and Wireless Access Point devices.
Replace existing electric water heater, in garage.
Replace existing 250 gallon water heater.
EVERSOURCE - 2nd Floor - New Executive Office space and reception area
2nd floor tent fitout
in order for site, preparation, anticipated work reflecting on ALT# 836506 with total cost reflecting on ALT# 836506
Conference room becoming a work space. Removing existing strobe and installing 1 ceiling mount horn/strobe. Also installing 1 smoke detector in new A/V closet
1 st floor
1 st floor
enlarging a conference room, painting, carpet, mill work, electrical, data, No fire alarm, No structural work,
Energy Mgmt, Offices, Utility Facility Certificate for the;Control Room/Pantry/Lavatories (2nd- floor EMC-Only ALT614707 issued: 8/3/16
Installation of 1 addressable relay to interface with new revolving door/"man trap" for release on fire alarm
Installing 2 strobes, 1 each in new conference and training rooms. Installing 2 horn/strobes in existing corridor. Installing 3 modules to bypass time delay crash bar doors
Strip and reroof.
Energy Mgmt, Offices, Utility Facility Temporary Certificate for the;Control room/Pantry/Lavatories (2nd floor EMC). Certificate expires in 90 days; 8/8/17 -;pending completion of…
Phase 1 of a 2 Phase project. Installation of 14 Horn/Strobes in Emergency Control room and surrounding office areas on 2nd floor. BFD permit filed, BFDF689538
Phase 2 of a 2 Phase Project. Installation of 1 Strobe and 3 Horn/strobes in 2nd floor office area. Phase 2 BFD # is BFDF689648. Phase 1 EFA is 689680 and BFDF689538
37009P-EVERSOURCE DORCHESTER TOILET ROOMS-ADDITIONAL FIXTURES
to install new emergency power off epo system for data and mdf rooms on the 1 st floor this epo system to be tied into the fire alarm system as supervisory point if the system loos…
37009P EVERSOURCE DORCHESTER TOILET ROOMS-REMOVE & REPLACE WATER CLOSETS & URNINALS
Replacement of existing plumbing fixtures on the 2nd floor.
modifications to optral standby generator lighting ups @power
Eversource is dividing old locker room into 3 space. New smaller locker room, temporary call canter, and a storage room. We're adding 1 pull station and 2 horn/strobes.
locker room demo unstall new data elc for temp office
1st floor
36053P-Eversource-Swing Space Demolition
Replace existing Generator, add new Generator. Replace UPS in kind. Replace CRAH AC in Kind. New DX AC unit. Control room renovation / New Video Monitor Map Board. In fill Light we…
Renovation of existing unoccupied locker room area into new locker room, office space, and storage room
Vacuum ballast EPDM, remove EPDM and install new Tremco built up roofing system. Sandblast underside of deck, install new bird netting
OFFICE INSTALLATION AND RELOCATION
OFFICE INSTALLATION AND RELOCATION
Construct Interior 25 x 20 Office Relocate Approximately 75 L.F of Wire Partition Relocate (4) Office Furniture Cubicles
Remove existing NSTAR sign faces.; Install new sign faces;to read :; EVERSOURCE ENERGY per BRA approved;drawings
Legal Occupancy:; Offices, Energy Managment, Utility Facility. doc. #1605/2009 ALT108224, Issued: 12/16/11 Certificate of Occupancy for 1st &; 2nd floors of NStar Offices
Wire (4) Boilers and (2) 230V Pumps and (2) 120V Pumps
Install 2 gas-fired boilers and 2 gas-fired water heaters
Install Water Heaters and 2 Storage Tanks
Install 3 - 3 phase 30A feeds to new vehicle lifts.
1st Floor Shower Room: Remove wall tiles on two walls; furnish and install new shower enclosure.
Proposed Work: Constructing a salt shed on the NStar property. Sitework and concrete to be done., Last Action: READY TO ISSUE
Nstar - 2nd floor Tenant renovations of existing offices rework two offices into 3. work includes demo, drywall partition, electrical, sprinkler, HVAC and finish work
renovate existing conference rooms to office
1st floor
NStar -; Amendment to;ALT 173543 (interior renovations).; Construction of a new 15' high exterior masonry Storage screen Wall.; The 3-sided wall will partially enclose steel storag…
Install 1 roof top unit
Relocae two fire alarm Horn/strobe in 1st fl restrooms
Renovate 1st floor restrooms
Renovate handicap bathrooms on 1st floor. Update plumbing, electrical, and finishes
Interior renovations to the first floor of Building A. Work to include construction of new vestibule with CMU walls, new ceiling, new flooring, relocating sprinkler heads, add one…
Removal of two doors and frames and select finished on the 1st floor in preparation of a future buildout.
Renovation to existing office space on 1st floor (NSTAR)
Renovation to existing office space on 1st floor (NSTAR)
Install 1 vent pipe on 1st floor
**Reinstallation of Water Cooler**
Add 2 hi-bay LED lights to building 'B'.
Installation of 3-1200A quick disconnect emergency switches - replace existing HVAC unit
NSTAR; Installation of Emergency Generator and Quick Disconnect Switches.; Replacement of Garage Men's Locker Room HVAC Unit. Work includes Electrical, Plumbing &; HVAC work.
remodeling existing bathrooms
plug together modular furniture for WB Mason furniture. Our electrical permit is seperate and tel/data is by others
replace existing fire alarm devices add ADA booster panels job is phased
rehab 2nd floor new lighting, relay sw panels, switches, occupancy sensors, recpt, furn feeds, HVAC & replace existing panelboards.
Nstar Swing Space - 1 &; 2nd floors Renovation includes demo, drywall, ceiling, flooring, HVAC, electrical, sprinkler, plumbing and finishes
Nstar -1&2nd floor Prep demo of interior space
Modify 3 small spaces for offices 1st and 2nd floors Nstar
Install new pedestal meter socket for Verizon equipment vault (To replace existing unit which was damaged)
demo, relocate, reuse and new lighting, switches, duplex, Wiremold, furn conn, 1 roof top unit and 100A subpanel
new FA horn strobes, duct tetector & test & smoke detectors
Prep demo of three existing suites 1st & 2nd floors
renovate existing work room> add funiture feeds. reswitch existing light fixtures
Nstar - 1st floor separate eziting room in middle with new GWB partition, relocate one sprinkler head, adjust existing supply and returns re-switch existing lights, NO new egress r…
Exterior lights recpt and 100A WP sub-panel fed fron an existing fused disconnect switch
Furnish and Install a new Tremco Cold Process Built-up Roof System over the open Canopy Roof Areas as per manufacturer's specifications and details. Clean and Paint underside of ex…
NStar storage shed wiring
Remove in its entirity a 15'x90' "salt" shed, at NSTAR's Mass Ave. Facility. The area will be turned into parking once the structure and foundations is removed Contact Alan Watson…
Installation of temp overhead service to power Guard shack @ Norfork street Gate
ENTERANCE DUCT BANK EXTENSION
Roof Replacement