Boston, MA
300 Terminal Rd has 224 municipal building permits on file in Ward 1. The latest recorded activity was a electrical permit dated Jul 22, 2026. Permits at this address represent $5MM–$25MM in total declared construction value.
Electrical
Fire Alarm
Electrical
Fire Alarm
Electrical
Electrical
3 other addresses on Terminal Rd with municipal permit records in Boston.
This address has 224 permit records in PropertyLabs' public history and is located in Ward 1. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 300 Terminal Rd is dated Jul 22, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 300 Terminal Rd in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Low Voltage
Electrical
Fire Alarm
Low Voltage
Fire Alarm
Low Voltage
Electrical
Electrical
Electrical
Fire Alarm
Low Voltage
Low Voltage
Electrical
Fire Alarm
Fire Alarm
Electrical
Low Voltage
Electrical
Electrical
Low Voltage
Low Voltage
Low Voltage
Fire Alarm
Fire Alarm
Fire Alarm
Fire Alarm
Fire Alarm
Fire Alarm
Low Voltage
Low Voltage
Low Voltage
Electrical
Low Voltage
Electrical
Low Voltage
Electrical
Electrical
Terminal E, Pre security. Install data in floor boxes for kiosks and D1 check-in.
Terminal E, Pre security. Install floor boxes for kiosks and D1 check-in.
Terminal A. Delta baggage. Install wiring for (2) HVAC units.
Common Use Gates (Volume 5): Selective demolition and installation of low voltage cabling, pathways, and devices to support common use gate, ticketing, DPIP, Wi Fi, paging, and IT…
Common Use Gates (Volume 5): Provide temporary power and lighting to support construction activities - 120V and 30 Amps in accordance with OSHA standards.
Common Use Gates (Volume 5): Work includes selective demolition and reinstallation of electrical power systems serving the Terminal B2C Common Use areas. Extend existing branch cir…
Common Use Gates(Vol5): Limited FA modifications to accommodate renos. Existing FA devices&circuits remain in service, w/devices temporarily removed, relocated, or reinstalled as r…
Dave's Hot Chicken. Terminal B, Space# BA2-A15. Renovation of existing restaurant. Install Cat 6 for POS and cameras
Dave's Hot Chicken. Terminal B, Space# BA2-A15. Renovation of existing restaurant. Relocate existing fire alarm devices as needed.
Dave's Hot Chicken. Terminal B, Space# BA2-A15. Renovation of existing restaurant. Install new receptacles and lighting.
Terminal AS, Space AS2-A03. Restaurant fit out Half Moon Empanadas. Install Cat 6 wiring for POS and cameras
Berkshire Farm, Terminal B, Space BA2-A33. Minor renovation of existing restaurant. Install Cat 6 for POS.
Berkshire Farm, Terminal B, Space BA2-A33. Minor renovation of existing restaurant. Install new receptacle for revised kitchen equipment.
Terminal A. Restaurant fit out called Half Moon Empanadas. Relocate existing fire alarm devices.
Terminal A. Restaurant fit out Half Moon Empanadas. Install new power and lighting.
One for one swap for jet bridge C27 at Terminal C. Disconnect cords from existing jet bridge and re-connect to new jet bridge.
Terminal C, (Former Natalies Candy) Install a new circuit for espresso machine and fridge.
Remodel of a restaurant Cava. Terminal B, Space BB2-A17. Install new power and lighting in kitchen. All panels are existing to remain.
Renovation of a restaurant Cava, Terminal B, Space BB2-A17. Test existing devices and replace as needed.
Renovation of existing restaurant Cava Terminal B, Space BB2-A17. Install new Cat 6 for Data, POS, and cameras.
Renovation of the Power to a retail kiosk at Gate C29 @ Terminal C - Gate 29
Renovation - data to a retail kiosk at Gate C29
Installation of receptacles for vending machines. Terminal A, B, C, & E.
Terminal A, Delta breakroom SI1316. Install a new circuit for a dryer and booster fan.
Install data wiring for new Dunkin Terminal A, Satellite.
Install new initiating and alerting devices for Dunkin Terminal A, Satellite.
Install power and lighting for new Dunkin Terminal A, Satellite. Install new 200A 120/208V panel.
C3 Club (Vol 2): Installation of new additional fire alarm devices including electrical conduit conductors & devices & modules for a complete & fully functional system. All work wi…
Terminal C Paging (Vol 4): Installation of new FA for including new FA conduit, conductors, devices &; modules for a complete&;fully functional system at Station 18 IT room. All wo…
Restroom Improvements (Volume 6): Installation of new fire alarm for including new FA conduit, conductors, devices & modules for a complete & fully functional system for restroom i…
FIS Corridor (Volume 3): Installation of temporary fire alarm devices for on the temporary FIS corridor and new FA conduit, conductors, devices & modules for a complete & fully fun…
FIS Corridor (Vol3 - Perm. FIS Corridor):Installation of temp FA devices for the temp FIS corridor&new FA conduit, conductors, devices&modules for a complete&fully functional syste…
FIS Corridor(Vol3 FIS Corridor Reno): Installation of temp FA devices for the temp FIS corridor & new FA conduit, conductors, devices & modules for a complete & fully functional sy…
FIS Corridor (Volume 3): Installation of Low Voltage systems infrastructure, pathways, cables, and devices for voice data, security systems, cameras, access control, and paging and…
Restroom Improvements (Volume 6): Installation of new PA infrastructure, pathways, cables, devices and speakers for restroom improvements. All work to follow and be coordinated wit…
FIS Corridor (Volume 3) (Permanent FIS Corridor): Installation of Low Voltage systems infrastructure, pathways, cables, and devices for voice data, security systems, cameras, acces…
FIS Corridor (Volume 3) (FIS Corridor Reno): Installation of Low Voltage systems infrastructure, pathways, cables, and devices for voice data, security systems, cameras, access con…
FIS Corridor (Volume 3) (Permanent FIS Corridor): Selective Demolition and of make safe electrical systems and new installation, new power distribution systems, lighting fixtures,…
FIS Corridor (Volume 3) (FIS Corridor Renovation): Selective Demolition and make safe electrical systems and new installation new power distribution systems, lighting fixtures, and…
FIS Corridor (Volume 3) (Permanent FIS Corridor): Provide temporary power and lighting to support construction activities of FIS Corridor - 120V and 30 Amps in accordance with OSHA…
FIS Corridor (Volume 3) (FIS Corridor Renovation): Provide temporary power and lighting to support construction activities of FIS Corridor - 120V and 30 Amps in accordance with OSH…
Terminal C Paging (Volume 4): Installation of Low Voltage systems infrastructure, pathways, cables, devices and speakers for paging at Terminal C. All work to follow and be coordin…
C3 Club (Volume 2): Provide temporary power and lighting to support construction activities - 120V and 30 Amps in accordance with OSHA standards.
Restroom Improvements (Volume 6) Provide temporary power and lighting to support construction activities at restroom renovations - 120V and 30 Amps in accordance with OSHA standard…
Restroom Improvements (Volume 6): Selective Demolition and make safe electrical systems and new installation new power GFCI receptacles, power for new automatic toilets flush, soap…
FIS Corridor (Volume 3): Provide temporary power and lighting to support construction activities of FIS Corridor - 120V and 30 Amps in accordance with OSHA standards.
Terminal C Paging (Volume 4): Selective Demolition and make safe electrical systems and new installation new power at station 18 IT room.
C3 Club (Volume 2): Selective Demolition and make safe electrical systems and new installation of medium voltage substation infrastructure, new power distribution systems included…
C3 Club (Volume 2): Installation of Low Voltage systems infrastructure, pathways, cables, and devices for voice data, security systems, cameras, access control, and paging includin…
FIS Corridor (Volume 3): Selective Demolition and make safe electrical systems and new installation new power distribution systems, lighting fixtures, and lighting controls, mechan…
Bunk Trailers: Installation of new additional fire alarm devices including electrical conduit conductors & devices & modules for a complete & fully functional system. All work will…
Install power for new UPS equipment.
Install a sub-panel and 4 receptacles for vending machines
Power, Lighting for a new JetBlue airline club space @ Terminal C - Departures Level
Renovation of the Fire Alarm for a new JetBlue airline club space @ Terminal C - Departures Level
Terminal A & AS. Install new countertop receptacles in various Delta breakrooms
E23028 MPA Term C relocate 3 FA speaker/strobes.
E23018 MPA Terminal C add two receptacles.
Terminal A, Gate A21. Install a 200 Amp feed for tug charger.
Installation of (1) 200amp - 277/480volt 3-phase load center and installation of (7) existing EV charging stations to new locations at Terminal C.
Renovation of Dunkin - Terminal C Gate 290
Furnish & install junction box conduit with pull strig and CAT6 cable for each of the (25) tell data devices location
One for one swap out of a 208v/60/3ph 5.9w at 16.4 amps skillet unit at Davio's Terminal C
Terminal A, Pre-security. Install new data for ticket kiosk relocation.
Terminal A, Pre-Security. Install new floor mounted raceway for ticket kiosks relocation
Terminal A, gates A1 to A11 & A13 to A17. Remove and re-install receptacles in gate millwork that is being replaced.
Terminal C badge office power, lighting, for small remodel. @ Terminal C - 1st floor Badge Office
Terminal C badge office renovation ,fire alarm for small remodel. @ Terminal C - 1st floor Badge Office
Terminal C badge low voltage wiring for small remodel. @ Terminal C - 1st floor Badge Office
Terminal A, Gates A1 to A11 & A13 to A17. Terminate existing Cat 6 cable after new gate millwork is installed.
F&I (2) cat 6 cables for the POS system at the front counter. F& I (2) cat 6 cables for the Receipt Printer system. Furnish and install (3) cat 6 cables for the Prep Printer system…
Installation of (5) Safe Gate Devices in Terminal C at gates C16, C23, C24, C25, and C36. Each safe gate device will have (1) 20-amp/120-Volt circuit and (5) Cat 6 lines installed.
FA for the remodel of an existing Dunkin store @ Terminal C arrivals level
Power, lighting for the remodel of an existing Dunkin store @ Terminal C arrivals level
Demo and make safe any cables and or equipment on the departures level bridge connecting Terminal C and E so that bridge can be removed @ Departures level bridge connecting Termina…
Installation of conduits and cables to serve 15 motors, totaling 48hp for a new baggage carousel at MU24. Remove existing 175amp breaker and install a new 225amp breaker; land new…
Power and lighting, for retail store @ Terminal C
renovation of low voltage for retail store @ Terminal C
Fire Alarm renovation for retail store @ 300 Terminal C
Terminal E. Install new receptacles for Delta Pilot Office. Install new sub panel.
Terminal E. Delta Pilot Office. Install new Cat 6 wiring for data.
Disconnect and make safe existing 240v electrical connections for (2) dishwashers at Davios in Terminal C for removal. Re-connect disconnecting means for two new dishwashing units…
Fire Alarm for retail store @ Terminal C
Power, lighting for retail store @ Terminal C - main hall
low voltage for retail store @ Terminal C
low voltage for retail store @ Terminal C - main hall
Power, lighting for retail store @ Terminal C
Disconnect four 120/208v service whips for kitchen equipment back to their respective junction box at Boston Beer Works in terminal C. This store is being closed permanently.
Swapping out one hardwired flat top unit for another. This will be a one-to-one swap out
Add 3 receptacles for countertop
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C36
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C25
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C24
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C23
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C16
Install 120v line and Cat 6 line to the Safe Gate in Terminal C, gate C16.
Tenant fit-out of a New England Collections retail store, Terminal A - Satellite. Install new lighting and power for cash wrap.
Tenant fit-out of a New England Collections retail store, Terminal A - Satellite. Install Cat 6 for cash wrap.
Installing a new conveyor belt for MU24 in Terminal C. Existing circuits will be demoed and reused to feed two 2hp motors and re-connect four e-stops.
Work is being done at Jet bridge 20 in terminal c. Intercepting feeds and installing two 200amp 480v meter sockets and two 200amp 480v disconnects and one 100amp 480v meter socket…
Intercept power for Jet bridge C-34 in terminal 3 and install two 200amp 480v 3ph meter sockets with two 200amp disconnects and one 100amp meter socket with one 100amp disconnect.
Intercepting power for Jet bridge C-29 in terminal C and installing two 200amp meter sockets with two 200 amp disconnects and one 100amp meter socket with one 100amp disconnect.
Make power safe at units on jet bridge. Relocate conduits to accommodate new jet bridge, install new conduits and needed conductors to re-energize all units associated with jet bri…
Restaurant fit-out for a new Shake Shack, Terminal C, Space CC2-A56
Restaurant fit-out for a Shake Shack, Terminal C, Space# CC2-A56
TENANT FIT OUT FOR A NEW RESTAURANT BUFFALO WILD WINGS. TERMINAL A SATELLITE SPACE AS2-A18
TENANT FIT OUT FOR A NEW RESTAURANT BUFFALO WILD WINGS. TERMINAL A SATELLITE SPACE AS2-A18
Tenant fit out for a new restaurant Buffalo Wild Wings. Terminal A Satellite Space AS2-A18
• Furnish & Install - Duplex Electrical at B22 and B8 podium • Furnish & Install - 2 Floor boxes
• Test and provide labeling information at existing gates B22 (3 data), B8 (4 data), B20 (2 data), B7 (3 data), B6 (2 data) & B18 (4 data) • Test and provide labeling information a…
Disconnecting power to motor and motor disconnects. Relocating new disconnect/control panel and reconnecting to new motors using existing power.
Install New 20 AMP circuit & receptacle @ Terminal C Logan Airport Mija Restaurant
Install one new data location @ Terminal C Logan Airport Mija Restaurant
Install a new 100A 120/208V service and 8 receptacles. Marketplace storage, Terminal C
Pulling existing circuits back to a junction box and then extending out to new equipment.
Add new 20 amp 120 volt circuit from panel to dedicated outlet approximately 40 feet away from panel.
Terminal A satellite. Restaurant fit-out for a Jimmy Johns. Install Cat 6 wiring for POS and cameras.
Terminal A satellite. Restaurant fit-out for a Jimmy Johns. Install new alerting and initiating devices.
Relocate a horn strobe device to new wall to serve existing area.
Removing 72 light fixtures and installing 72 new LED light fixtures
Adding 2-4 receptacles on two newly constructed non-bearing walls. Relocating one audio/visual fire alarm device and adding one camera and key card access panel.
Remove 100amp disconnect from ceiling and install next to new hot water tank location. Install a junction box for connections of feeder wires to be extended to new location.
Demo existing control panel and install new control panel and any necessary wiring.
Demo existing circuits and equipment for carousel 8 and install new disconnect/control panel with start stop switches for motor and door controls.
Fit out for new retail store @ DUFRY SPACE CB2-A09 - TERMINAL C
Fit out for new retail store @ DUFRY SPACE CB2-A09 - TERMINAL C
Fit out for new retail store @ DUFRY SPACE CB2-A09 - TERMINAL C
Terminal A Satellite. Install new power and lighting for restaurant fit out.
Terminal A satellite. Fox & Flight restaurant. Install new alerting and initiating devices.
Terminal A Satellite. Fox & Flight restaurant. Install low voltage cabling for POS and speakers.
Demo existing emergency stop switches, both motors, control panel and disconnecting means and then relocate and install new gear, motors and emergency stop switches.
LV for new retail store @ DUFRY - TEMP SPACE CM2-A57
Fit out for new retail store @ DUFRY - TEMP SPACE CM2-A57
Add receptacles for new equipment @ Terminal C Starbucks 2nd floor secure side - space CE6
Add data drops for POS equipment @ Terminal C Starbucks 2nd floor secure side - space CE6
Terminal C, Pier B, Space CB2-A10. Install power and lighting for new restaurant Gachi Sushi & Noodles.
Renovation of Hudson Store. Terminal C, Space CB2-A16/28A
Connect replacement griddle at STEPHANIE'S restaurant
Install data devices in new cashwrap. Hudson Space SL1 Terminal C
Install receptacles in new cashwrap. Hudson Space CB2-A25/CE1. Terminal C
Install receptacles in new cashwrap. Hudson Space SL1 Terminal C
Install data outlets for new cashwrap. Hudson Space CB2-A25/CE1. Terminal C
Make safe and remove 3 sign feeds @ Logan Airport - Terminal C - 2nd floor secure side
Wire replacement, hot water heater
Connect 3 replacement 120v refrigerators at STEPH E
Modify Emergency Electrical Feeds to Air Traffic Control Supply
Install Cat 6 wiring for POS system
Install lighting and power for Hudson/Dunkin store. Hudson/Dunkin Terminal B/C Connector Space CD2A58/A59
Install lighting and power for new Hudson retail store. Terminal B/C Connector Space BA2-A40
Install initiating and alerting devices for retail store. Hudson/Dunkin Terminal B/C Space CD2A58 & A59
Install Cat 6 wiring for POS system Hudson Terminal B/C Space BA2-A20
Install new initiating and alerting devices. Hudson Terminal B/C Connector Space BA2-A40
Install Cat 6 Wiring for POS system Hudson/Dunkin Terminal B/C Connector Space CD2A58 & A59
Demo all wiring for the covid testing setup at Term C location
Replace 4 existing 3pole 30A breakers with 4 new 3pole 30A shunt trip breakers @ Wahlburgers, Terminal C 2nd floor
Renovation of Hudson Store. Terminal E
Install track lighting and receptacles for coolers in new Hudson storage room. Terminal B, Pier B
Connect 230v circuit at display case, and connect 230v replacement dishwasher at DINE BOSTON
Hudson Store. Terminal B - Pier B Space BA2-A28/BA-A30 Minor renovation. Remove valance lights. Install receptacles for cooler lights.
Delta Sky Club Terminal E. Install receptacles for new kitchen equipment.
Install a new 75KVA transformer and 200 Amp panel. Install receptacles in new Delta office space.
Install new data outlets for Delta office space, Terminal E
Demo 4 outlets and install 3 new @ Terminal C - Logan Airport 2nd floor storage room
Tenant Fit Out - Airport Lounge @ 300 Terminal RD, Terminal C to B Connector - 4th Floor - Logan Airport
Tenant Fit Out - Airport Lounge @ 300 Terminal RD, Terminal C to B Connector - 4th Floor - Logan Airport
Connect replacement Fryolator in kitchen
E18046 Make safe demo and temporary lights.
Install power and data for new self checkout at Hudson News Terminal E
Install power and data for new self checkout at Hudson News Terminal C
Install power and data for new self checkout at Hudson News Terminal B, BB2-A15
Install power and data for new self checkout at Hudson News Terminal B, BA2-A18/BA-A14
Install Disconnect and receptacle for deicing
ETS permit to temporarily connect temporary generator to emergency system while new emergency system is being constructed for 6 month
Replacement of defective switchboard