Building permit intelligence · Boston, MA
324 Huntington Av has 63 municipal building permits on file in Ward 4. The latest recorded activity was a lvolt permit dated Jul 21, 2026. Permits at this address represent $1MM–$5MM in total declared construction value. PropertyLabs also identified 4 mapped permits within 2 km of this address.
Low Voltage
Renovations - Interior NSC
Plumbing
Renovations - Interior NSC
Low Voltage
Low Voltage
4 mapped permits within 2 km, shown on the intelligence map above.
12 other addresses on Huntington Av with municipal permit records in Boston.
This address has 63 permit records in PropertyLabs' public history and is located in Ward 4. The city figures below provide context without changing the focus of this exact-address record.
City coverage counts address-linked rows and does not add overlapping canonical tables. Rolling windows are inclusive, use UTC boundaries, and end Aug 1, 2026.
PropertyLabs compiled this permit history from municipal public records for Boston, MA. The latest recorded permit activity at 324 Huntington Av is dated Jul 21, 2026. Municipal records can be corrected or updated after publication.
See the contractors, applicants, permit holders, permit numbers, and project documents associated with 324 Huntington Av in the PropertyLabs platform, along with alerts when new permits are filed at this address.
Electrical
Low Voltage
Fire Alarm
Plumbing
Electrical
Fire Alarm
Demolition - Interior
Low Voltage
Renovations - Interior NSC
Plumbing
Electrical
Interior/Exterior Work
Renovations - Interior NSC
Low Voltage
Renovations - Interior NSC
Fire Alarm
Electrical
Demolition - Interior
Low Voltage
Low Voltage
Electrical
Dodge Hall Room 150 Classroom Upgrade. Includes new flooring. remove and replace existing wall panels, relocate/add outlets for new TV's, replace existing ceiling tiles, and paint.
Electrical
Installation of a new IT closet that will serve the AV needs for Dodge Hall.
Install 12 Cat6 cables and 7 AV cables to 18 classrooms
We will be doing a lighting retrofit through out the building.
Install lighting and outlets per plan Room 301 Dodge Building
Install lighting and outlets per plan Room 201 Dodge Building
Install 3 new V/D locations.
Install 3 new V/D locations.
install 1 sink
Install 1 - 1Voice/3Data location in Rm 152, 474 and 350
install 2 new V/D locations
Removal of existing fire pump system and installation of new FP bypass.
Removal existing fire pump. (Dodge Hall)
Install 16 Voice/Data locations
Install lighting and outlets per plan Install 3 office furniture connections Dodge Building 4th Floor
Install 4 Horn strobes and 1 detector Dodge building Room 450
Library, Classrooms, School C/O-For Offices, Conference Rooms &; Common Areas -at Dodge Hall to the 1st floor -only alt 511905 issued 9/1/15, sf 501706 issued 8/3/15
Install 4 V/D locations
Interior renovation to approximately 7500 sq ft at Dodge Hall to the 1st floor conference rooms, offices and common corridors. Work to include; sprinkler, FA, MEP's and architectur…
Interior demolition to approximately 4000 sf on the first floor of Dodge Hall. Removal of interior paritions, doors ceilings, flooring, electrical and HVAC elements.
Install lighting and outlets per plan Dodge building ground floor
Subdivision of existing offices to create an additional office space. Work to include minor demolition, metal framing and GWB, electrical, HVAC, and minor sprinkler work.
Install 5 new V/D locations
150 Dodge Building Install lighting and outlets per plan
Install 12 Voice/Data locations
Renovation of existing Classroom. Scope of work to include minor electrical,minor HVAC and A/V upgrades
Selective demolition of finishes including ceilings, lighting, non-load bearing drywall partitions, and carpet. No structural demo or demo of fire alarm or sprinkler systems.
Install wiring and devices for Office area remodel.
renovate existing office space #rd floor at dodge hall. work to include paint, carpet, door replacement, minor carpentry and minor electrical.
Legal Occupancy:; Library, Classrooms, School COO for offices on the 1st floor Alt224083, issued: 3/18/13
Instal 2 new horn strobes to plan
Installation of voice and data locations
Dodge 152 Install lighting and outlets per plan
Communication Suite - First Floor - Actual address is 324 Huntington Ave. not in data base Renovate existing offices into New Communication &; PR Suite to include elec, HVAC,plumbi…
Renovate classroom 201 Mugar hall per the attached plans &; specifications. Scope of work to include new seating, finishes, HVAC, Electrical, sprinkler improvements.